Contract
No: HK/2011/07 Wanchai Development Phase
II and Sampling, Field Measurement and
Testing Works
(Stage 2) Environmental Permit no. EP-356/2009, Further Evironmental permit nos.
fep-01/356/2009, fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009 and Fep-05/356/2009 Monthly Environmental Monitoring & Audit Report
- august 2012 -
|
CLIENTS: |
|
Civil Engineering and Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
11 September 2012 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. Status of Regulatory Compliance
3.1 Status of Environmental Licensing and Permitting under
the Project
5.2 Real-time Noise Monitoring
6.2 Real-time noise Monitoring
6.5 Review of the Reasons for and the Implications of
Non-compliance
6.6 Summary of action taken in the event of and follow-up
on non-compliance
7. Cumulative Construction Impact due to the Concurrent
Projects
9. Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table I Summary
of Water Quality Monitoring Exceedances in Reporting Month
Table II Summary
of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month
Table 2.1 Schedule 2
Designated Projects under this Project
Table 2.2 Details
of Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/11
Table 3.3 Summary
of submission status under FEP-01/356/2009 Condition
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Table 3.5 Summary
of submission status under FEP-02/356/2009 Condition
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Table 3.7 Summary
of submission status under FEP-03/356/2009 Condition
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/15
Table 3.9 Summary
of submission status under FEP-04/356/2009 Condition
Table 3.10 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2010/06
Table 3.11 Summary of
submission status under EP-356/2009 and FEP-05/356/2009 Condition
Table 3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/19
Table 4.1 Noise
Monitoring Station
Table 4.2 Real
Time Noise Monitoring Station
Table 4.3 Air
Monitoring Station
Table 4.4 Marine Water
Quality Stations for Water Quality Monitoring
Table 4.5 Marine
Water Quality Monitoring Frequency and Parameters
Table 4.6 Marine
Water Quality Stations for Enhanced Water Quality Monitoring
Table 4.7 Marine
Water Quality Stations for Additional DO Monitoring
Table 5.1 Noise
Monitoring Stations for Contract no. HY/2009/11
Table 5.2 Noise
Monitoring Station for Contract nos. HK/2009/01, HK/2009/02 and HK/2010/06
Table 5.3 Noise
Monitoring Station for Contract no. HY/2009/15
Table 5.4 Noise
Monitoring Station for Contract no. HY/2009/19
Table 5.5 Real
Time Noise Monitoring Station for Contract no. HY/2009/11 and HY/2009/19
Table 5.6 Air
Monitoring Stations for Contract no. HY/2009/11
Table 5.7 Air
Monitoring Stations for Contract no. HK/2009/01
Table 5.8 Air
Monitoring Station for Contract no. HK/2009/02
Table 5.9 Air
Monitoring Station for Contract no. HY/2009/15
Table 5.10 Air
Monitoring Stations for Contract no. HY/2009/19
Table 5.11 Water
Monitoring Stations for Contract no. HY/2009/11
Table 5.12 Water
Monitoring Stations for Contract no. HK/2009/01
Table 5.13 Water
Monitoring Stations for Contract no. HK/2009/02
Table 5.14 Water
Monitoring Stations for Contract no. HK/2010/06
Table 5.15 Water
Monitoring Stations for Contract no. HY/2009/15
Table 5.16 Water
Monitoring Stations for Contract no. HY/2009/19
Table 5.17 Summary
of Water Quality Monitoring Exceedances in Reporting Month
Table 5.18 Summary
of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month
Table 5.19 Details of
Waste Disposal for Contract no. HK/2009/01
Table 5.20 Details of
Waste Disposal for Contract no. HK/2009/02
Table 5.21 Details of
Waste Disposal for Contract no. HY/2009/15
Table 5.22 Details of
Waste Disposal for Contract no. HK/2010/06
Table 5.23 Details of Waste
Disposal for Contract no. HY/2009/19
Table 8.1 Summary of
Environmental Inspections for Contract no. HK/2009/01
Table 8.2 Summary of
Environmental Inspections for Contract no. HK/2009/02
Table 8.3 Summary of
Environmental Inspections for Contract no. HY/2009/15
Table 8.4 Summary of
Environmental Inspections for Contract no. HK/2010/06
Table 8.5 Summary
of Environmental Inspections for Contract no. HY/2009/19
Table 9.1 Cumulative
Statistics on Complaints
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Table 10.1 Construction
Activities and Recommended Mitigation Measures in Coming Reporting Month
lIST
OF FIGUREs
Figure 2.2 Project Organization Chart
Figure 2.3 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical Presentations
Appendix 5.3 Air Quality Monitoring Results and Graphical Presentations, and Odour Patrol Results
Appendix 5.4 Water Quality Monitoring Results and Graphical Presentations
Appendix 5.4a Additional Dissolved Oxygen Monitoring Results
Appendix 5.5 Real-time Noise Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Summary for Notification of Exceedance
Appendix 8.1 Construction Programme of Individual Contracts
Construction Activities for the Reported Period
¡P
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19.
Marine
Works (at Wan Chai)
¡P
Rockfilling for rock bund
across HKCEC Water Channel from Ch220 to Ch230
¡P
Reclamation of HKCEC3W
within HKCEC Water Channel
¡P
Installation of pipe pile
wall for demolition of existing seawall at
¡P
Demolition of Wan Chai West Ferry Pier
Cross-Harbour
Watermains Installation (CHA & CHB) and Marine Works (at TST)
¡P
Rockfilling and rock
protection to cross-harbour watermains
¡P
Installation of
cross-harbour watermains No. A18 & B18
Fresh
Watermains, Cooling Watermains and Salt Watermains (On Land)
¡P
Mainlaying works at Zone
B1-5A, B2-1, B3-1, B4-3, B4-1A, B5-1(Switch Room), B5-3(Switch Room), A1-1,
A1-2, A1-3B, A2-2, A3-2A, A3-4B, A3-5B and A4-2A
¡P
The reinstatement of one
carriageway at Zone B2-1 Mainlaying Works at Zone B3-1 of Expo Drive Central
¡P
Breakup of concrete
surround and trimming of 1 no. existing intake and 2 no. existing discharge
pipe at Zone A1-1 and A1-2
¡P
Pipe laying works at
Heading No. H7
¡P
Heading No. H6c (Mainlaying
works by trenchless method)
¡P
Mainlaying and chamber
construction works at the traffic island near junction of
¡P
Mainlaying works at Zone
A3-2A of
¡P
Mainlaying works at
¡P
Mainlaying Works for a 1000
dia. Watermains (CHE) at
¡P
Reinstatement Works at
¡P
Pipe Laying works including
9 nos. cooling mains across E/D section within HKCEC Water Channel
¡P
Pipe Laying works including
9 nos. cooling mains across SCL section within HKCEC Water Channel
¡P
Pipe Laying works including
9 nos. cooling mains and 2no. cross harbour watermains at North Bank of HKCEC
Water Channel
¡P Modification
work of PTI and bus station at
¡P Self-testing
of the individual pumping systems for cooling mains work
¡P Wet
well was handed over to E & M for penstock leakage testing
¡P Reinstatement
at
¡P Cooling
mains installation at west of Gate 1 inside ex-pet garden and the steel
fixing and casting of the damaged
thrust box
¡P Cabling
works along
¡P Waterproofing
membrane at roof level at WSD Salt Water Pumping Station.
¡P E&M
works at WSD Salt Water Pumping Station
¡P Wall
shaft and roof slab casting of salt water intake culvert at Wan Shing Street
Bay 20 and steel fixing of 19B
¡P Removing
the strut & waling for road reinstatement near Bay 24 and backfilling of
salt water intake culvert at
¡P Sheetpiling
at Bay 11 and the grouting work
¡P Pile
cap steel fixing of Bay
¡P Concreting
the salt water intake culvert of Bay 4 and Bay 7 at WCR1 and concreting the
base slab of Bay 8
¡P Concreting
pile cap of IC1 and the construction of pile cap IC2 in salt water intake seaside
cofferdam.
¡P Excavation
and breaking up the rock down to 3rd layer of strut and waling installation of
the outfall launching shaft and then the 2nd layer waling
¡P Cutting
the opening of sheetpiles and coring of thrust wall between Launching Pit and
Jacking Pit
¡P Excavation
the fill material to expose HDPE pipe end by divers inside the outfall seaside
cofferdam
¡P Cutting
casing of pre-bored H-pile to cut-off level for pile cap at Bay 4 and Bay 5 of
Box Culvert N1 northern cofferdam
¡P Excavation
to formation level and making good of blinding layer for pile cap at Bay 4 and
Bay 5 of Box Culvert N1 northern cofferdam
¡P Concreting
the base slab of Box Culvert N1 Bay 2 and Bay 3 on UU bridge
¡P Dismantling
of steel panel & H-beam of water tank at zone 2B and the dismantling work
of water tank in zone 3B and
¡P Concreting
the columns at New Ferry Pier GL 6-7 / B-F level 1 to level 2 and erection
formwork and falsework at GL 8-15 / B-F
¡P Steel
fixing the slab at New Ferry Pier GL 1-8 level 1 and GL 9 -15 level 2
¡P Rockfilling
and placing bagged concrete for the seawall block area at WCR2
¡P Reclamation
of WCR2
¡P TDMP
for Box Culvert ¡§O¡¨ Diversion at Bay 12-13
¡P Bulkhead
wall at
¡P Water
pressure test and sterilization test for 150MS freshwater pipe at Box Culvert ¡§O¡¨
prior to the diversion of captioned water pipe.
¡P Trial
pit excavation and preparation works for Hung Hing Road Diversion
¡P Removal
of temporary reclamation at TS1
¡P Underwater
cutting of temporary diaphragm walls at TS1
¡P Dredging
for seawall foundation at TS2
¡P Seawall
trench works at TS2
¡P Pile
head breaking
¡P Sonic
tube trimming
¡P
Marine bored piling
¡P
Construction works for Box Culvert T
Real-time
Noise Monitoring
Air Quality Monitoring
CMA1b: from 27 Jul and 20 August 2012 to 31 Jul and
21 August 2012
CMA2a: from 27 Jul and 8 August 2012 to 28 Jul and
10 August 2012
CMA5a: from 20 August 2012 to 21 August 2012
CMA6a: from 8 August 2012 to 9 August 2012
CMA2a: from 9 August 2012 to 11 August 2012
Water Quality Monitoring
Table I Summary of Water Quality Monitoring Exceedances in
Reporting Month
Contract
no. |
Water
Monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
|||||||||
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|||
HY/2009/11 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring finished on 6 Feb 2012 |
WSD10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD15 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C8 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/01 |
WSD19 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C3 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C4e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C4w |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring finished on 27 April 2012 |
WSD20 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
HK/2009/01 & HK/2010/06 |
C2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C5w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
1 |
|
Monitoring started on 8 Feb 2012 |
WSD21 |
0 |
0 |
0 |
0 |
2 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
|
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HY/2009/15 |
C7 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HY/2009/19 Monitoring started on 28 Jan 2012 |
C8 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
1 |
|
C9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
Total |
2 |
0 |
0 |
0 |
4 |
0 |
1 |
0 |
0 |
2 |
2 |
2 |
||
Remarks: -
The
cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the
water monitoring at C6 was then terminated since 17 May 2011.
-
WSD9 and WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.
- 4-week water quality monitoring at
WSD9, WSD10, WSD15, WSD17, C8 and C9 were completed on 6 Feb 2012.
- C8 and C9 were implemented with
respect to HY/2009/19 from 28 Jan 2012.
- WSD7 and WSD20 water quality
monitoring were temporarily suspended from 27 Apr 2012.
Table II Summary of Enhanced
Dissolved Oxygen Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
|
LL |
|
LL |
||
HY/2009/15 |
C6 |
0 |
0 |
0 |
0 |
C7 |
2 |
0 |
0 |
0 |
|
Ex-WPCWA SW |
0 |
0 |
0 |
4 |
|
Ex-WPCWA SE |
5 |
0 |
4 |
3 |
|
Total |
7 |
0 |
4 |
7 |
Complaints, Notifications of Summons and Successful
Prosecutions
Site Inspections and Audit
Future Key Issues
Contract no. HY/2009/11- North Point
Reclamation
¡P
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19 on 31 December 2011.
Contract no. HK/2009/01 - Wan Chai
Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC
Marine Works
¡P
Reclamation works within HKCEC Water Channel (from
CH170 to CH220)
¡P
Rockfilling for formation of rock bund within HKCEC
Water Channel (from CH220 to CH230)
¡P
Installation pipe pile wall for modification of
vertical seawall near
¡P
Rockfilling at northeast of Area 9 and Area7 near
¡P
Demolition of Wan Chai West Ferry Pier
¡P
Cross-Harbour Watermains Installation (CHA &
CHB) Trust block construction, concrete coating for flange joint and
rockfilling protection works for cross-harbour watermains in Victoria Harbour
¡P
Reinstatement works at TST seashore including
removal of silt screen and dismantling of jack-up barge
Fresh
Watermains, Cooling Watermains and Salt Watermains (On Land)
¡P
Zone B1-5A, B2-1, B4-1A, B4-3, B5-1, B5- 3, A1-1,
A1-2, A1-3B, A2-2, A3-2A, A3-4B, A3-5B, A4-2A
¡P
Mainlaying works and G.I. ducting works at Zone
B1-5A, B4-1A and B4-3
¡P
Mainlaying works at Zone B3-1
¡P
Mainlaying works across the run-out of Renaissance
Harbour View Hotel by open-cut method
¡P
Mainlaying works at
¡P
Mainlaying works at traffic island near junction
between
¡P
Pipe laying works at Zone A3-2A would be completed
and heading no. H1
¡P
Mainlaying works at Zone A3-5B of
¡P
No. H6C excavation works.
¡P
Pipe laying works for cross harbour watermains
within HKCEC water channel
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
¡P
Complete PTI modification works after completion of
New Public Toilet in
¡P
Complete the initial testing of P7, P8 and P9
pumping station.
¡P
Complete all cooling mains and cabling works for P7,
P8 & P9 Pumping Stations permanent power-on and signal control.
¡P
800MS pipe installation inside
¡P
ABWFs & E&M works of WSD Salt Water Pumping
Station.
¡P
Conduct Fire Service Inspection of WSD Salt Water Pumping Station
¡P
Complete the finishing works of WSD Salt Water
Pumping Station.
¡P
Complete WSD intake A and Intake B in-situ concrete
work.
¡P
Construction of Bay 1b ¡V 2, Bay 6 ¡V 8 salt water
intake culverts at WCR1 area.
¡P
Continue construction salt water intake
¡P
Commence salt water intake culvert at transition
bays inside jacking pit and receiving pit.
¡P
Continue remaining drainage works and reinstatement
works along
¡P
Commence HDPE piping on UU Bridge and inside
launching pit.
¡P
Construction for Box Culvert N1 at WCR1 area.
¡P
Complete concreting works for the Level 2 at the
New Ferry Pier.
¡P
Reclamation works at WCR2 area.
¡P
Commence drainage work to suit TWCR4 construction.
¡P
Diversion of uncharted drainage works at Box
culvert ¡§O¡¨.
¡P
Continue trial excavation and preparation works for
Hung Hing Road Diversion
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V
Tunnel (
¡P
TZ1 reclamation works
¡P
Seawall trench works at TS2
¡P
Formation of temporary seawall at TS2
¡P
Dredging at TS2
¡P
Pile head breaking
¡P
Sonic tube trimming
Contract no. HY/2009/19- Wan Chai
Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
¡P
Construction works for Box Culvert T
¡P
Marine Piling
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to
work as the Environmental Team (ET) under Environmental Permit no. EP-356/2009
and Further Environmental permit nos. FEP-01/356/2009, FEP-02/356/2009,
FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009 to implement the
Environmental Monitoring and Audit (EM&A) programme as stipulated in the
EM&A Manual of the approved Environmental Impact Assessment (EIA) Report
for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.:
AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring
and auditing work carried out in accordance to the Section 10.3 of EM&A
Manual and ¡§Environmental Monitoring and Audit Requirements¡¨ under
Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A works
for Environmental Permit no. EP-356/2009, Further Environmental Permit no.
FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and
FEP-05/356/2009 and during the period of July
to August. The cut-off
date of reporting is at 27th of each reporting month.
Section 1 Introduction ¡V details the
scope and structure of the report.
Section 2 Project
Background ¡V summarizes background and scope of the project, site
description, project organization and contact details of key personnel during
the reporting period.
Section 3 Status of Regulatory Compliance ¡V summarizes the
status of valid Environmental Permits / Licenses during the reporting period.
Section 4 Monitoring
Requirements ¡V summarizes all monitoring parameters, monitoring
methodology and equipment, monitoring locations, monitoring frequency, criteria
and respective event and action plan and monitoring programmes.
Section 5 Monitoring
Results ¡V summarizes the monitoring results obtained in the
reporting period.
Section 6 Compliance Audit ¡V summarizes the auditing of monitoring results, all exceedances
environmental parameters.
Section 7 Cumulative Construction Impact due to the Concurrent Projects ¡V summarizes the relevant cumulative construction impact due to the
concurrent activities of the concurrent Projects.
Section 8 Site Inspection ¡V summarizes the findings of weekly site
inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.
Section 9 Complaints, Notification of summons and Prosecution ¡V summarizes the cumulative statistics on complaints, notification of summons and
prosecution
Section 10 Conclusion
2.1.1.
¡§Wan Chai Development phase II and Central-Wan Chai
Bypass¡¨ and ¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨
(hereafter called ¡§the Project¡¨) are Designed Project (DP) under the
Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental
Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The key purpose of Wan Chai Development Phase II
(WDII) is to provide land at Wan Chai North and North Point for construction of
the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed
under the project will be developed as a world-class waterfront promenade
joining that at the new Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB
to provide relief to the very congested
2.2.1.
The Project is located mainly in Wan Chai North,
2.2.2.
The study area encompasses existing developments
along the Wan Chai,
2.2.3.
The scope of the Project comprises:
¡P
Land
formation for key transport infrastructure and facilities, including the Trunk
Road (i.e.
CWB) and the associated slip roads for connection to the Trunk Road and for through
traffic from Central to Wan Chai and Causeway Bay. The land formed for the above
transport infrastructure will provide opportunities for the development of an attractive
waterfront promenade for the enjoyment of the public
¡P
Reprovisioning
/ protection of the existing facilities and structures affected by the land
formation works mentioned above
¡P
Extension,
modification, reprovisioning or protection of existing storm water drainage
outfalls, sewerage outfalls and watermains affected by the revised land use and
land formation works mentioned above
¡P
Upgrading
of hinterland storm water drainage system and sewerage system, which would be
rendered insufficient by the land formation works mentioned above
¡P
Provision
of the ground level roads, flyovers, footbridges, necessary transport
facilities and the associated utility services
¡P
Construction
of the new waterfront promenade, landscape works and the associated utility
services
¡P
The
Trunk Road (i.e. CWB) within the study area and the associated slip roads for
connection to the Trunk Road.
2.2.4.
The project also contains various Schedule 2 DPs
that, under the EIAO, require Environmental Permits (EPs) to be granted by the
DEP before they may be either constructed or operated. Table 2.1
summarises the five individual DPs under this Project. Figure 2.1 shows the
locations of these Schedule 2 DPs.
Table 2.1 Schedule
2 Designated Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason for
inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project,
there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced. Contractors of individual contracts will
be required by the EP holder to apply Further Environmental Permits (FEP) such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized
in Table 2.2.
Table 2.2 Details
of Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
25 August 2011 |
||
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 April 2011 |
||
HY/2009/11 |
Wan Chai Development Phase II and Central ¡V Wan Chai Bypass ¡V North Point
Reclamation |
DP3 |
17 March 2010 (Under application of surrender) |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel ( |
DP3 |
10 November 2010 |
DP1 |
13 July 2011 |
||
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central - Wan Chai Bypass (CWB) ¡V Central Interchange |
DP1 |
21 April 2011 |
HY/2009/19 |
Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the
construction phase of the Project, Project Engineer, Contractor(s), Environmental
Team and Independent Environmental Checker are appointed to manage and control
environmental issues.
2.4.2.
The proposed project organization and lines of
communication with respect to environmental protection works are shown in Figure
2.2. Key personnel
and contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of
Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer¡¦s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer¡¦s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3922 8332 |
3529 2829 |
|
|
Contractor under Contract no. HY/2009/11 |
Project Director |
Mr. Cho Yu Fun |
3157 1086 |
3157 1085 |
Project
Manager |
Mr. Gregory Wong |
3157 1086 |
|||
Site Agent |
Mr. Daniel Cheung |
3157 1086 |
|||
Environmental
Officer |
Mr. C. M. Wong |
3157 1086 |
|||
Chun Wo ¡V Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Director |
|
2162 9909 |
2587 1878 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Sub-Agent |
Mr Terry Wong |
9757 9846 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack Chu |
9775 3008 |
|||
Construction
Manager |
Mr. KK Yuen |
9498 1213 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Quality & Environmental Manager (Environmental Officer) |
Mr. C.P. Ho |
3658 3000 |
|
||
|
Contractor under Contract no. HY/2009/15 |
Project Director |
Chan Wai Hung |
2823 7813 |
2865 5229 |
Site Manager |
P J Fan |
3557 6368 |
2566 2192 |
||
|
|
Contractor¡¦s Representative |
Mr. David Lau |
3557 6358 |
|
|
|
Head of Construction Manager |
Roger Cheung |
3557 6371 |
|
|
|
Senior Construction Manager |
Gene Cheung |
3557 6395 |
|
|
|
Environmental Officer |
Mr. Daniel Sin |
3557 6347 |
|
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529 2880 |
Site Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental
Officer |
Mr. Lee Wai Man |
9481 6024 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Cheung Kit Cheung |
6909 1555 |
|||
Environmental
Engineer |
Mr. Calvin Leung |
9286 9208 |
|||
Environmental Manager / Environmental
Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Yung Kwok Wah |
9834 1010 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
For Contract no. HY/2009/11, the principal work
activities in this reporting month included:
¡P
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19
on 31 December 2011.
2.4.4.
For Contract no. HK/2009/01, the principal work
activities in this reporting month included:
Marine Works
(at Wan Chai)
¡P
Rockfilling for rock bund
across HKCEC Water Channel from Ch220 to Ch230
¡P
Reclamation of HKCEC3W
within HKCEC Water Channel
¡P
Installation of pipe pile
wall for demolition of existing seawall at
¡P
Demolition of Wan Chai West
Ferry Pier
Cross-Harbour
Watermains Installation (CHA & CHB) and Marine Works (at TST)
¡P
Rockfilling and rock
protection to cross-harbour watermains
¡P
Installation of
cross-harbour watermains No. A18 & B18
Fresh
Watermains, Cooling Watermains and Salt Watermains (On Land)
¡P
Mainlaying works at Zone B1-5A,
B2-1, B3-1, B4-3, B4-1A, B5-1(Switch Room), B5-3(Switch Room), A1-1, A1-2,
A1-3B, A2-2, A3-2A, A3-4B, A3-5B and A4-2A
¡P
The reinstatement of one
carriageway at Zone B2-1 Mainlaying Works at Zone B3-1 of Expo Drive Central
¡P
Breakup of concrete
surround and trimming of 1 no. existing intake and 2 no. existing discharge
pipe at Zone A1-1 and A1-2
¡P
Pipe laying works at
Heading No. H7
¡P
Heading No. H6c (Mainlaying
works by trenchless method)
¡P
Mainlaying and chamber
construction works at the traffic island near junction of
¡P
Mainlaying works at Zone
A3-2A of
¡P
Mainlaying works at
¡P
Mainlaying Works for a 1000
dia. Watermains (CHE) at
¡P
Reinstatement Works at
¡P
Pipe Laying works including
9 nos. cooling mains across E/D section within HKCEC Water Channel
¡P
Pipe Laying works including
9 nos. cooling mains across SCL section within HKCEC Water Channel
¡P
Pipe Laying works including
9 nos. cooling mains and 2no. cross harbour watermains at North Bank of HKCEC
Water Channel
2.4.5.
For Contract no. HK/2009/02, the principal work
activities in this reporting month included:
¡P
Modification work of PTI
and bus station at
¡P
Self-testing of the
individual pumping systems for cooling mains work
¡P
Wet well was handed over to
E & M for penstock leakage testing
¡P
Reinstatement at
¡P
Cooling mains installation
at west of Gate 1 inside ex-pet garden and the steel fixing and casting of the damaged thrust box
¡P
Cabling works along
¡P
Waterproofing membrane at roof
level at WSD Salt Water Pumping Station.
¡P
E&M works at WSD Salt
Water Pumping Station
¡P
Wall shaft and roof slab
casting of salt water intake culvert at Wan Shing Street Bay 20 and steel
fixing of 19B
¡P
Removing the strut &
waling for road reinstatement near Bay 24 and backfilling of salt water intake
culvert at
¡P
Sheetpiling at Bay 11 and
the grouting work
¡P
Pile cap steel fixing of
Bay
¡P
Concreting the salt water
intake culvert of Bay 4 and Bay 7 at WCR1 and concreting the base slab of Bay 8
¡P
Concreting pile cap of IC1
and the construction of pile cap IC2 in salt water intake seaside cofferdam.
¡P
Excavation and breaking up
the rock down to 3rd layer of strut and waling installation of the outfall
launching shaft and then the 2nd layer waling
¡P
Cutting the opening of
sheetpiles and coring of thrust wall between Launching Pit and Jacking Pit
¡P
Excavation the fill
material to expose HDPE pipe end by divers inside the outfall seaside cofferdam
¡P
Cutting casing of pre-bored
H-pile to cut-off level for pile cap at Bay 4 and Bay 5 of Box Culvert N1 northern
cofferdam
¡P
Excavation to formation
level and making good of blinding layer for pile cap at Bay 4 and Bay 5 of Box
Culvert N1 northern cofferdam
¡P
Concreting the base slab of
Box Culvert N1 Bay 2 and Bay 3 on UU bridge
¡P
Dismantling of steel panel
& H-beam of water tank at zone 2B and the dismantling work of water tank in
zone 3B and
¡P
Concreting the columns at
New Ferry Pier GL 6-7 / B-F level 1 to level 2 and erection formwork and
falsework at GL 8-15 / B-F
¡P
Steel fixing the slab at
New Ferry Pier GL 1-8 level 1 and GL 9 -15 level 2
¡P
Rockfilling and placing
bagged concrete for the seawall block area at WCR2
¡P
Reclamation of WCR2
¡P
TDMP for Box Culvert ¡§O¡¨
Diversion at Bay 12-13
¡P
Bulkhead wall at
¡P
Water pressure test and sterilization
test for 150MS freshwater pipe at Box Culvert ¡§O¡¨ prior to the diversion of
captioned water pipe.
¡P
Trial pit excavation and
preparation works for Hung Hing Road Diversion
2.4.6.
For Contract no. HY/2009/15, the principal work
activities in this reporting month included:
¡P
Removal of temporary
reclamation at TS1
¡P
Underwater cutting of
temporary diaphragm walls at TS1
¡P
Dredging for seawall
foundation at TS2
¡P
Seawall trench works at TS2
2.4.7.
For Contract no. HK/2010/06, the principal work
activities in this reporting month included:
¡P
Pile head breaking
¡P
Sonic tube trimming
2.4.8.
For Contract no. HY/2009/19, the principal work
activity in this reporting month included:
¡P
Construction works for Box Culvert T
¡P
Marine Piling
2.4.9.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract no. HY/2009/11- North Point
Reclamation
¡P
The
major work activities for Contract no. HY/2009/11 was confirmed substantial
complete by RSS on 4 January 2012. The construction site was handed over to contractor HY/2009/19 on 31
December 2011.
Contract no. HK/2009/01 - Wan Chai
Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC
Marine Works
¡P
Reclamation works within HKCEC Water Channel (from
CH170 to CH220)
¡P
Rockfilling for formation of rock bund within HKCEC
Water Channel (from CH220 to CH230)
¡P
Installation pipe pile wall for modification of
vertical seawall near
¡P
Rockfilling at northeast of Area 9 and Area7 near
¡P
Demolition of Wan Chai West Ferry Pier
¡P
Cross-Harbour Watermains Installation (CHA &
CHB) Trust block construction, concrete coating for flange joint and
rockfilling protection works for cross-harbour watermains in Victoria Harbour
¡P
Reinstatement works at TST seashore including
removal of silt screen and dismantling of jack-up barge
Fresh
Watermains, Cooling Watermains and Salt Watermains (On Land)
¡P
Zone B1-5A, B2-1, B4-1A, B4-3, B5-1, B5- 3, A1-1,
A1-2, A1-3B, A2-2, A3-2A, A3-4B, A3-5B, A4-2A
¡P
Mainlaying works and G.I. ducting works at Zone
B1-5A, B4-1A and B4-3
¡P
Mainlaying works at Zone B3-1
¡P
Mainlaying works across the run-out of Renaissance
Harbour View Hotel by open-cut method
¡P
Mainlaying works at
¡P
Mainlaying works at traffic island near junction
between
¡P
Pipe laying works at Zone A3-2A would be completed
and heading no. H1
¡P
Mainlaying works at Zone A3-5B of
¡P
No. H6C excavation works.
¡P
Pipe laying works for cross harbour watermains
within HKCEC water channel
Contract no.
HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
WanChai East
¡P
Complete PTI modification works after completion of
New Public Toilet in
¡P
Complete the initial testing of P7, P8 and P9
pumping station.
¡P
Complete all cooling mains and cabling works for P7,
P8 & P9 Pumping Stations permanent power-on and signal control.
¡P
800MS pipe installation inside
¡P
ABWFs & E&M works of WSD Salt Water Pumping
Station.
¡P
Conduct Fire Service Inspection of WSD Salt Water Pumping Station
¡P
Complete the finishing works of WSD Salt Water
Pumping Station.
¡P
Complete WSD intake A and Intake B in-situ concrete
work.
¡P
Construction of Bay 1b ¡V 2, Bay 6 ¡V 8 salt water
intake culverts at WCR1 area.
¡P
Continue construction salt water intake
¡P
Commence salt water intake culvert at transition
bays inside jacking pit and receiving pit.
¡P
Continue remaining drainage works and reinstatement
works along
¡P
Commence HDPE piping on UU Bridge and inside
launching pit.
¡P
Construction for Box Culvert N1 at WCR1 area.
¡P
Complete concreting works for the Level 2 at the
New Ferry Pier.
¡P
Reclamation works at WCR2 area.
¡P
Commence drainage work to suit TWCR4 construction.
¡P
Diversion of uncharted drainage works at Box
culvert ¡§O¡¨.
¡P
Continue trial excavation and preparation works for
Hung Hing Road Diversion
Contract no. HY/2009/15 -
Central-Wanchai Bypass ¡V Tunnel (
¡P
TZ1 reclamation works
¡P
Seawall trench works at TS2
¡P
Formation of temporary seawall at TS2
¡P
Dredging at TS2
Contract no. HK/2010/06 - Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
¡P
Pile head breaking
¡P
Sonic tube trimming
Contract no. HY/2009/19 ¡V Central- Wan
Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
¡P
Construction
works for Box Culvert T
¡P
Marine
Piling
3.1.1.
A summary of the current status on licences and/or
permits on environmental protection pertinent to the Project is shown in Table
3.1.
Permits and/or
Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental
Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Under application of surrender |
Further Environmental
Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental
Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Valid |
Further Environmental Permit |
FEP-01/364/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-02/364/2009 |
21 Apr 2010 |
Valid |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
Valid |
Further Environmental Permit |
FEP-04/364/2009/A |
14 Oct 2010 |
Surrendered |
Further Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-07/364/2009/A |
25 Feb 2011 |
Valid |
Further Environmental Permit |
FEP-08/364/2009/A |
15 Jun 2012 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project,
the status of permits and/or licences under the individual contract(s) are
presented as below:
Contract no. HY/2009/11 ¡V
Central ¡V Wanchai Bypass, North Point Reclamation
3.1.3.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19 on 31 December 2011.
3.1.4.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission under
FEP-01/356/2009 for contract no. HY/2009/11 are shown in Table 3.2 and
Table 3.3.
3.1.5.
Contractor submitted a letter dated 20 July 2011 to
confirm that the dredging works and dumping operation were completed.
Table 3.2 Cumulative Summary of Valid Licences and
Permits under Contract
no. HY/2009/11
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
N/A |
Valid |
Notification of Works Under APCO |
331892 |
4 Jul. 2011 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-151-C3631-02 |
12 Oct 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance |
7010037 |
13 Jan 2010 |
N/A |
Valid |
Discharge Licence |
WT00007942-2010 |
29 Nov 2010 |
30 Nov 2015 |
Valid |
Table 3.3 Summary of
submission status under FEP-01/356/2009 Condition
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management
Organization of Main Construction Companies |
18 Dec 2009 |
Condition 2.7 |
Submission of works
schedule and location plan |
8 Feb 2010 |
Condition 2.8 |
Revised Silt Curtain
Deployment Plan (Rev. 3) |
4 Dec 2010 |
Condition 2.9 |
Silt Screen
Deployment Plan (Rev. 6) |
18 May 2011 |
Condition 2.10 |
Coral Translocation
Plan |
20 Nov 2009 |
Condition 2.16 |
Revised Noise
Management Plan (Rev 5) |
19 Feb 2011 |
Condition 2.17 |
Landscape Plan |
12 May 2010 |
|
Revised landscape Plan |
30 Jun 2010 |
|
Submission of
Supplementary Information - Revised Management & Maintenance Schedule for
Submitted Revised Landscape Plan |
25 Aug 2010 |
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
3.1.6.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission for contract no.
HK/2009/01 under FEP-02/356/2009 are shown in Table 3.4 and
Table 3.5.
Table 3.4 Cumulative Summary
of Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise
Permit (CNP) for non-piling equipment |
GW-RS0356-12 |
03 Apr 2012 |
11 Apr 2012 to 29 Sep 2012 |
Valid |
|
GW-RS0394-12 |
16 Apr 2012 |
19 Apr 2012 to 12 Oct 2012 |
Valid |
|
GW-RS0806-12 |
3 Aug 2012 |
4 Aug 2012 to 03 Feb 2013 |
Valid |
GW-RS0855-12 |
16 Aug 2012 |
17 Aug 2012 to 9 Feb 2013 |
Valid |
|
GW-RS0862-12 |
20 Aug 2012 |
28 Aug 2012 to 27 Feb 2013 |
Valid |
|
|
GW-RS0823-12 |
3 Aug 2012 |
3 Aug 2012 to 02 Feb 2013 |
Valid |
|
GW-RS0852-12 |
16 Aug 2012 |
16 Aug 2012 to 01 Feb 2013 |
Valid |
|
GW-RS0158-12 |
24 Feb 2012 |
24 Feb 2012 to 23 Aug 2012 |
Expired |
|
GW-RS0181-12 |
24 Feb 2012 |
27 Feb 2012 to 23 Aug 2012 |
Expired |
|
GW-RS0213-12 |
28 Feb 2012 |
29 Feb 2012 to 27 Aug 2012 |
Expired |
|
GW-RS0225-12 |
14 Mar 2012 |
13 Sep 2012 |
Valid |
GW-RS0227-12 |
2 Mar 2012 |
16 Mar 2011 to 15 Sep 2012 |
Valid |
|
GW-RE0174-12 |
5 Mar 2012 |
30 Mar 2012 to 29 Sep 2012 |
Valid |
|
GW-RS0312-12 |
28 Mar 2012 |
30 Mar 2012 to 29 Sep 2012 |
Valid |
|
GW-RS0545-12 |
24 May 2012 |
26 May 2012 to 25 Nov 2012 |
Valid |
|
GW-RS0546-12 |
25 May 2012 |
26 May 2012 to 25 Nov 2012 |
Valid |
|
GW-RS0460-12 |
10 May 2012 |
13 May 2012 to 6 Nov 2012 |
Valid |
|
|
GW-RS0514-12 |
14 May 2012 |
27 May 2012 to 26 Nov 2012 |
Valid |
GW-RS0731-12 |
5 Jul 2012 |
05 Jul 2012 to 01 Jan 2013 |
Cancelled |
|
GW-RS0760-12 |
18 Jul 2012 |
20 Jul 2012 to 19 Jan 2013 |
Valid |
|
GW-RS0771-12 |
23 Jul 2012 |
23 Jul 2012 to 31 Aug 2012 |
Valid |
|
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
|
Billing account under Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Dumping Permit (Type 1 ¡V |
EP/MD/13-004 |
23 May 2012 |
24 May 2012
to 23 Nov 2012 |
Valid |
Permit for Dumping at Sea - Dredged Sediment
Requiring Type 3 ¡V Special Treatment / Disposal contained in Geosynthetic
Containers |
EP/MD/13-030 |
3 Jul 2012 |
6 Jul 2012
to 5 Aug 2012 |
Expired |
Table 3.5 Summary of
submission status under FEP-02/356/2009 Condition
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main Construction
Companies |
13 Apr 2010 |
Condition 2.7 |
Works Schedule and
Location Plan |
8 Apr 2010 |
Condition 2.8 |
Silt Curtain
Deployment Plan (Rev. 5) |
23 Aug
2012 |
Silt Curtain
Deployment Plan (Rev. 4) |
12 Jul
2012 |
|
Condition 2.9 |
Silt Screen
Deployment Plan |
19 Apr 2010 |
Conditions 2.8 and
2.9 |
Supplementary
Document on Silt Curtain and Silt Screen Deployment Plan |
19 Jul 2010 |
Report on Field
Testing for Silt Curtain |
26 Aug 2010 |
|
Report on Field
Testing for Silt Curtain (Rev. A) |
15 Nov 2010 |
|
Condition 2.12(d) |
Alternative Proposal
on Concurrent Dredging for Sewage Pipeline and |
15 Apr 2011 |
Condition 2.17 |
Noise Management
Plan |
23 Apr 2010 |
Condition 2.18 |
Landscape Plan
(Erection of Decorative Screen Hoarding along Construction Site around |
15 May 2010 |
|
Landscape Plan
(Night-time Lighting) |
22 Oct 2010 |
|
Landscape Plan (Rev.
B) |
15 Nov 2010 |
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
3.1.7.
Summary of the current status
on licences and/or permits on environmental protection pertinent and submission
for contract no. HK/2009/02 under FEP-03/356/2009 are shown in Table 3.6 and
Table 3.7.
Table 3.6 Cumulative Summary
of Valid Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
|
|
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for piling
equipment |
PP-RS0007-12 |
27 Mar 2012 |
28 Mar 2012
to 27 Sept 2012 |
Cancelled |
Construction Noise Permit (CNP) for non-piling
equipment |
GW-RS0671-12 |
25 June 2012 |
17 Jul 2012 to 16 Jan 2013 |
Valid |
|
GW-RS0730-12 |
9 July 2012 |
10 Jul 2012 to 8 Jan 2013 |
Valid |
|
GW-RS0736-12 |
9 July 2012 |
9 Jul 2012 to 8 Jan
2013 |
Valid |
|
GW-RS0870-12 |
21 Aug 2012 |
16 Sept 2012 to 31 Dec 2012 |
Valid |
|
GW-RS0037-12 |
19 Jan 2012 |
1 Feb 2012 to 31 July 2012 |
Expired |
|
GW-RS0051-12 |
19 Jan 2012 |
1 Feb 2012 to 31 July 2012 |
Cancelled |
|
GW-RS0105-12 |
3 Feb 2012 |
10 Feb 2012 to 9 Aug 2012 |
Cancelled |
|
GW-RS0153-12 |
17 Feb 2012 |
21 Feb 2012 to 20 Aug 2012 |
Cancelled |
|
GW-RS0255-12 |
14 Mar 2012 |
17 Mar 2012 to 15 Sept 2012 |
Valid |
|
GW-RE0283-12 |
5 Apr 2012 |
1 May 2012 to 30 Nov 2012 |
Valid |
|
GW-RS0739-12 |
9 July 2012 |
1 Aug 2012 to 31 Jan 2013 |
Valid |
|
GW-RS0301-12 |
20 Mar 2012 |
21 Mar 2012 to 20 Sept 2012 |
Cancelled |
|
GW-RS0303-12 |
26 Mar 2012 |
27 Mar 2012 to 27 Sept 2012 |
Valid |
|
GW-RS0341-12 |
3 Apr 2012 |
28 Apr 2012 to 27 Oct 2012 |
Valid |
|
GW-RS0348-12 |
3 Apr 2012 |
10 Apr 2012 to 9 Oct 2012 |
Valid |
|
GW-RS0380-12 |
12 Apr 2012 |
1 May 2012 to 31 Oct 2012 |
Valid |
|
GW-RS0388-12 |
13 Apr 2012 |
1 May 2012 to 31 Oct 2012 |
Valid |
GW-RS0418-12 |
30 Apr 2012 |
23 May 2012 to 22 Nov 2012 |
Valid |
|
GW-RS0420-12 |
30 Apr 2012 |
18 May 2012 to 17 Nov 2012 |
Cancelled |
|
GW-RS0423-12 |
30 Apr 2012 |
19 May 2012 to 18 Nov 2012 |
Cancelled |
|
GW-RS0427-12 |
30 Apr 2012 |
23 May 2012 to 22 Nov 2012 |
Valid |
|
GW-RS0445-12 |
30 Apr 2012 |
1 May 2012 to 25 Sept 2012 |
Valid |
|
GW-RS0814-12 |
3 Aug 2012 |
6 Aug 2012 to 5 Dec 2012 |
Valid |
|
GW-RS0533-12 |
21 May 2012 |
21 May 2012 to 10 Nov 2012 |
Valid |
|
GW-RS0850-12 |
10 Aug 2012 |
14 Aug 2012 to 13 Feb 2013 |
Valid |
|
GW-RS0550-12 |
25 May 2012 |
7 June 2012 to 6 Dec 2012 |
Valid |
|
GW-RS0611-12 |
14 June 2012 |
15 Jun 2012 to 28 Nov 2012 |
Valid |
|
GW-RS0633-12 |
13 June 2012 |
16 Jun 2012 to 14 Dec 2012 |
Valid |
|
Discharge Licence |
WT00006249-2010 |
22 Mar 2010 |
31 Mar 2015 |
Valid |
|
WT00006436-2010 |
15 Apr 2010 |
30 Apr 2015 |
Valid |
WT00006673-2010 |
14 May 2010 |
31 Mar 2015 |
Cancelled |
|
WT00006757-2010 |
28 May 2010 |
31 May 2015 |
Valid |
|
WT00007129-2010 |
28 July 2010 |
31 Jul 2015 |
Valid |
|
WT00008982-2011 |
26 April 2011 |
30 April 2016 |
Valid |
|
WT00009691-2011 |
1 Aug 2011 |
31 July 2016 |
Valid |
|
Billing Account under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance (Marine) |
7011496 |
6 Oct 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Dumping Permit (Type 1 ¡V |
EP/MD/13015 |
25 May 2012 |
29 May 2012 to 28 Nov 2012 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type
2 ¡V Confined Marine disposal) |
EP/MD/13-046 |
27 July 2012 |
6 Aug 2012 to 5 Sept 2012 |
Valid |
Table 3.7 Summary of
submission status under FEP-03/356/2009 Condition
EP Condition |
Submission |
Date of Submission |
Condition 1.12 |
Commencement Date of
Construction of Marine Works |
8 April 2010 |
Condition 2.6 |
Management
Organization of Main Construction Companies |
10 April 2010 |
Condition 2.7 |
Works Schedule and
Location Plans |
8 April 2010 |
Condition 2.8 |
Silt Curtain
Deployment Plan (Revision A) |
20 April 2010 |
Silt Curtain
Deployment Plan (Revision B) |
25 May 2010 |
|
Silt Curtain
Deployment Plan (Revision C) |
14 Jun 2010 |
|
Silt Curtain
Deployment Plan (Revision H) |
15 Feb 2011 |
|
Silt Curtain
Deployment Plan (Revision I) |
17 Nov 2011 |
|
Silt Curtain
Deployment Plan (Revision J) |
15 Feb 2012 |
|
Silt Curtain
Deployment Plan (Revision K) |
3 May 2012 |
|
Condition 2.9 |
Silt Screen
Deployment Plan |
21 April 2010 |
Supplementary
Information for Existing WSD Salt Water Intakes at |
5 Oct 2010 |
|
Silt Screen
Deployment Plan (Revision B) |
15 Feb
2012 |
|
Silt Screen
Deployment Plan (Revision C) |
3 May 2012 |
|
Condition 2.17 |
Noise Management
Plan |
6 May 2010 |
Condition 2.18 |
Landscape Plan
(Decorative Screen Hoarding) |
11 May 2010 |
Landscape Plan
(Control of Night Time Lighting) |
2 June 2010 |
|
|
Landscape Plan
(Combined Version) |
20 July 2011 |
Landscape Plan
(Combined Version) |
5 Aug 2011 |
|
----- |
Acknowledge of
Submission |
22 Aug 2011 |
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V
Tunnel (
3.1.8.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission for contract no.
HY/2009/15 under EP-356/2009 are shown in Table 3.8 and
Table 3.9.
Table 3.8 Cumulative Summary
of Valid Licences and Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
FEP-06/364/2009/A |
22 Nov 2010 |
N/A |
Valid |
|
FEP-01/416/2011 |
11 Nov 2011 |
N/A |
Valid |
|
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Construction Noise
Permit (CNP) for Filling and Diaphragm Wall Works at TS4/ME4 |
GW-RS0249-12 |
10 Feb 2012 |
9 Mar 2012 to 31 Aug 2012 |
Valid |
Construction Noise
Permit (CNP) for non-piling equipment |
GW-RS0343-12 |
12 Apr 2012 |
13 Apr 2012
to 8 Oct 2012 |
Valid |
Construction Noise
Permit (CNP) for Removal Works at TS1 |
GW-RS0607-12 |
12 Jun 2012 |
13 Jun 2012 to 7 Dec 2012 |
Valid |
Registration as a
Chemical Waste Producer |
WPN5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance |
7011553 |
30 Sep 2010 |
27 Sep 2010 to 27 Jan 2016 |
Valid |
7011761 |
10 Jul 2012 |
17 Jul 2012 to 16 Oct 2012 |
Valid |
|
Dumping Permit (Type 1 ¡V |
EP/MD/13-018 |
6 Jun 2012 |
6 Jun 2012 to 5 Dec 2012 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate
Sites) & Type 2 ¡V Confined Marine disposal) |
EP/MD/13-048 |
30 Jul 2012 |
8 Aug 2012 to 7 Sep 2012 |
Valid |
EP/MD/13-037 |
3 Jul 2012 |
8 Jul 2012 to 7 Aug 2012 |
Expired |
Table 3.9 Summary of submission
status under FEP-04/356/2009 Condition
FEP Condition |
Submission |
Date of Submission |
Condition 2.7 |
Works Schedule and Location Plans |
27 Oct 2010 |
|
Amendment for Works Schedule and Location Plans |
12 Nov 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan |
30 Nov 2010 |
|
Amendment for Silt Curtain Deployment Plan |
24 Feb 2011 |
Amendment for Silt Curtain Deployment Plan |
11 May 2011 |
|
Condition 2.9 |
Silt Screen
Deployment Plan |
19 Oct 2010 |
Amendment for
Silt Screen Deployment Plan |
18 Feb 2011 |
|
Amendment for Silt Screen Deployment Plan |
15 Jun 2011 |
|
Condition 2.18 |
Proposal for
the Removal of Odorous Sediment and Slime |
13 Jan 2011 |
Amendment for Proposal for the Removal of
Odorous Sediment and Slime |
8 Mar 2011 |
|
Amendment for Proposal for the Removal of
Odorous Sediment and Slime |
2 Aug 2011 |
|
Condition 2.21 |
Landscape Plan |
18 Feb 2011 |
Condition 2.23 |
Noise Management Plan |
20 Oct 2010 |
|
Amendment for Noise Management Plan |
27 Jan 2011 |
3.1.9.
Implementation status of the recommended mitigation
measures during this reporting period is presented in Appendix 3.1.
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line
3.1.10.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission for contract no. HK/2010/06
under EP-356/2009 are shown in Table 3.10 and Table 3.11.
Table 3.10 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2010/06
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
N/A |
Valid |
FEP-08/364//2009/A |
15 June 2012 |
N/A |
Valid |
|
Notification of Works Under APCO |
326344 |
18 Jan 2011 |
N/A |
Valid |
Construction Noise Permit (CNP) for piling
equipment |
PP-RS0012-12 |
18 June 2012 |
6 Jul 2012 to 5 Jan 2013 |
Valid |
Construction Noise
Permit (CNP) for non-piling equipment |
GW-RS0313-12 |
27 Mar 2012 |
6 Apr to 5 Oct 2012 |
Valid |
GW-RS0658-12 |
21 June 2012 |
13 Jul 2012 to 12 Jan 2013 |
Valid |
|
Billing Account under Waste Disposal Ordinance |
7012338 |
16 Feb 2011 |
N/A |
Valid |
Registration as Chemical Waste Producer |
WPN5213-134-G2533-01 |
11 Feb 2011 |
N/A |
Valid |
Water Discharge
Licence |
WT00010905-2011 |
4 November 2011 |
31 July 2016 |
Valid |
Dumping Permit (Type 1 ¡V |
EP/MD/12-122 |
9 Feb 12 |
12 Feb 2012 to 11 Aug 2012 |
Expired |
Table 3.11 Summary
of submission status under EP-356/2009 and FEP-05/356/2009 Condition
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main Construction Companies |
24 October 2011 |
Condition 2.7 |
Works Schedule and Location Plans |
11 March 2011 |
Condition 2.8 |
Revised Silt Curtain Deployment Plan |
31 Aug 2011 |
Condition 2.9 |
Silt Screen Deployment Plan |
11 April 2011 |
Condition 2.23 |
Noise Management Plan |
11 March 2011 |
Contract no. HY/2009/19 ¡V Central- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
3.1.11.
Summary of the current status on licences and/or
permits on environmental protection pertinent for contract no. HY/2009/19 is
shown in Table 3.12.
Table 3.12 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/19
Permit / Licence / Notification /
Approval |
Reference No. |
Issued Date |
Valid Period / Expiry date |
Status |
Further Environmental Permit |
FEP-07/364/2009/A |
25 Feb 2011 |
Granted |
Valid |
Notification of Works Under APCO |
326160 |
24 Jan 2011 |
Notified |
Valid |
Construction Noise
Permit (CNP) (For D-wall construction) |
GW-RS0180-12 |
22-Feb-12 |
26-Aug-12 |
Expired |
GW-RS0871-12 |
27-Aug-12 |
26-Feb-13 |
Valid |
|
Construction Noise
Permit (CNP) (For Bored pile construction at Portion III) |
GW-RS0507-12 |
22-May-12 |
23-Nov-12 |
Cancelled |
Construction Noise
Permit (CNP) (For Bored pile construction at Portion III, V) |
GW-RS0885-12 |
27-Aug-12 |
26-Feb-13 |
Valid |
Construction Noise
Permit (CNP) (For |
GW-RS0589-12 |
18-Jun-12 |
17-Dec-12 |
Valid |
Discharge Licence (Land) |
WT00010093-2011 |
17 Aug 2012 |
30-Sept-16 |
Valid |
Discharge Licence (Sea) |
WT00010865-2011 |
03 Nov 2011 |
30-Nov-16 |
Valid |
Registration as a
Waste Producer |
7012306 |
21 Jan 2011 |
Registered |
- |
C&D Waste Disposal |
7012306 |
10 Feb 2011 |
Registered |
- |
Vessel Disposal |
7013285 |
21 July 2011 |
Registered |
- |
Registration as Chemical Waste Producer |
5213-151-C3654-01 |
24 Mar 2011 |
Registered |
Valid |
Dumping Permit (Type 1 ¡V |
EP/MD/12-150 |
14-May-12 |
14-Nov-12 |
Valid |
Noise Monitoring Stations
4.1.1.
The noise monitoring stations for the Project are
listed and shown in Table 4.1 and Figure 4.1. Appendix 4.1 shows the
established Action/Limit Levels for the monitoring works.
Table 4.1 Noise Monitoring Station
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire
Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
Real-time Noise Monitoring
Stations
4.1.2.
The real-time noise monitoring stations for the
Project are listed and shown in Table 4.2 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.2 Real Time Noise Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison Centre |
Noise Monitoring
Parameters, Frequency and Duration
4.1.3.
The construction noise level shall be
measured in terms of the A-weighted equivalent continuous sound pressure level
(Leq). Leq (30 minutes) shall be used as the monitoring
parameter for the time period between 0700 and 1900 hours on normal weekdays.
For all other time periods, Leq (5 minutes) shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria. Supplementary
information for data auditing, statistical results such as L10 and L90 shall
also be obtained for reference.
4.1.4.
Noise monitoring shall be carried out at all the
designated monitoring stations. The monitoring frequency shall depend on the
scale of the construction activities. The following is an initial guide on the
regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
¡P
one
set of measurements between 0700 and 1900 hours on normal weekdays.
4.1.5.
If construction works are extended to include works
during the hours of 1900 ¡V 0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
Monitoring Equipment
4.1.6.
As referred to in the Technical Memorandum ™ issued
under the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring.
Immediately prior to and following each noise measurement the accuracy of the
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. Measurements may be accepted
as valid only if the calibration level from before and after the noise
measurement agree to within 1.0 dB.
4.1.7.
Noise measurements shall not be made in fog, rain,
wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s.
The wind speed shall be checked with a portable wind speed meter capable of
measuring the wind speed in m/s.
Air Quality Monitoring
Stations
4.2.1.
The air monitoring stations for the Project are
listed and shown in Table 4.3 and Figure
4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.3 Air Monitoring
Station
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil Street Community
Liaison Centre |
North Point |
CMA2a |
|
|
CMA3a |
CWB PRE Site Office * |
|
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds
opposite to |
Wan Chai |
CMA6a |
WDII PRE Site Office * |
Wan Chai |
* Remarks: As
per the ENPC meeting in January 2011, the monitoring stations CMA3a - Future
CWB site office at Wanchai Waterfront Promenade and CMA6a - Future AECOM site
office at Work Area were renamed as remark.
Air Monitoring Parameters,
Frequency and Duration
4.2.2.
One-hour and 24-hour TSP levels should be measured
to indicate the impacts of construction dust on air quality. The 24-hour TSP
levels shall be measured by following the standard high volume sampling method
as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part
50), Appendix B.
4.2.3.
All relevant data including temperature, pressure,
weather conditions, elapsed-time meter reading for the start and stop of the
sampler, identification and weight of the filter paper, and any other local
atmospheric factors affecting or affected by site conditions, etc., shall be
recorded down in detail.
4.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and
Monitoring Equipment
4.2.5.
High volume samplers (HVSs) in compliance with the
following specifications shall be used for carrying out the 1-hour and 24-hour
TSP monitoring:
¡P
0.6
- 1.7 m3 per minute adjustable flow range;
¡P
equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
¡P
installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
¡P
capable
of providing a minimum exposed area of 406 cm2;
¡P
flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
¡P
equipped
with a shelter to protect the filter and sampler;
¡P
incorporated
with an electronic mass flow rate controller or other equivalent devices;
¡P
equipped
with a flow recorder for continuous monitoring;
¡P
provided
with a peaked roof inlet;
¡P
incorporated
with a manometer;
¡P
able
to hold and seal the filter paper to the sampler housing at horizontal
position;
¡P
easily
changeable filter; and
¡P
capable
of operating continuously for a 24-hour period.
4.2.6.
Initial calibration of dust monitoring equipment
shall be conducted upon installation and thereafter at bi-monthly intervals.
The transfer standard shall be traceable to the internationally recognized
primary standard and be calibrated annually. The concern parties such as IEC
shall properly document the calibration data for future reference. All the data
should be converted into standard temperature and pressure condition.
Laboratory Measurement /
Analysis
4.2.7.
A clean laboratory with constant temperature and
humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
4.2.8.
An alternative non-HOKLAS accredited
laboratory was set-up for carrying out the laboratory
analysis, the laboratory equipment was approved by the ER on 8 February 2011 and the measurement procedures were
witnessed by the IEC. Any measurement performed by the laboratory was
be demonstrated to the satisfaction of the ER and IEC. IEC shall regularly
audit to the measurement performed by the laboratory to ensure the accuracy of
measurement results.
4.2.9.
Filter paper of size 8" x 10" shall be
labelled before sampling. It shall be a clean filter paper with no pinholes,
and shall be conditioned in a humidity-controlled chamber for over 24-hours and
be pre-weighed before use for the sampling.
4.2.10.
After sampling, the filter paper loaded with dust
shall be kept in a clean and tightly sealed plastic bag. The filter paper shall
then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
4.2.11.
All the collected samples shall be kept in a good
condition for 6 months before disposal.
impact monitoring for
odour patrol
4.2.12.
Odour patrols along the shorelines of Causeway Bay
Typhoon Shelter and ex-Wan Chai Public Cargo Working Area when there is
temporary reclamation in Causeway Bay Typhoon Shelter and/or in the ex-Wan Chai
Public Cargo Working Area, or when there is dredging of the odorous sediment
and slime at the south-western corner of the Causeway Bay Typhoon Shelter.
Odour patrols will be carried out at bi-weekly intervals during July, August
and September by a qualified person of the ET who shall:
¡P
be
at least 16 years of age;
¡P
be
free from any respiratory illnesses; and
¡P
not
be allowed to smoke, eat, drink (except water) or use chewing gum or sweets 30
min
¡P
before
and during odour patrol
4.2.13.
Odour patrol shall be conducted by independent
trained personnel / competent persons patrolling and sniffing around the shore
as shown in Figure
4.1 to detect any odour at the concerned hours (afternoon is
preferred for higher daily temperature).
4.2.14.
The qualified person will use the nose (olfactory
sensor) to sniff odours at different locations. The main odour emission sources
and the areas to be affected by the odour nuisance will be identified.
4.2.15.
The perceived odour intensity is to be divided into
5 levels which are ranked in the descending order as follows:
¡P
0 -
Not detected. No odour perceived or an odour so weak that it cannot be easily characterized
or described;
¡P
1 -
Slight Identifiable odour, and slight chance to have odour nuisance;
¡P
2 -
Moderate Identifiable odour, and moderate chance to have odour nuisance;
¡P
3 -
Strong Identifiable, likely to have odour nuisance;
¡P
4 -
Extreme Severe odour, and unacceptable odour level.
4.2.16.
The findings including odour intensity, odour
nature and possible odour sources, and also the local wind speed and direction
at each location will be recorded. In addition, some relevant meteorological
and tidal data such as daily average temperature, and daily average humidity,
on that surveyed day will be obtained from the Hong Kong Observatory Station
for reference. The Action and Limit levels for odour patrol are shown in Appendix
6.1.
4.2.17.
The qualified odour patrol member has individual
n-butanol thresholds complied with the requirement of European Standard Method
of Air Quality ¡V Determination of Odour Concentration by Dynamic Olfactometry
(EN13725) in the range of 20 to 80 ppb. The certificate for the qualified odour
panel member is shown in Appendix
4.2.
4.3.1.
The EIA Report has identified that the key water
quality impact would be associated with the dredging works during the
construction phase. Marine water quality monitoring for dissolved oxygen (DO),
suspended solid (SS) and turbidity is therefore recommended to be carried out
at selected WSD flushing water intakes. The impact monitoring should be carried
out during the proposed dredging works to ensure the compliance with the water
quality standards.
4.3.2.
The updated EM&A Manual for EP-356/2009
(Version in March 2011) is approval by EPD on 29 April 2011. As such, the
Action Level and Limit Level for the wet season (April ¡V September) will be
effected and applied to the water quality monitoring data from 30 April 2011.
Water Quality Monitoring Stations
4.3.3.
It is proposed to monitor the water quality at 9
WSD salt water intakes and 14 cooling water intakes along the seafront of the
Table 4.4 Marine Water Quality
Stations for Water Quality Monitoring
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD7 |
|
834150.0 |
818300.3 |
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
|
839790.3 |
817032.2 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
|
830750.6 |
816030.3 |
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
RW1 |
Wan Chai (Reprovision) |
836188.8 |
815911.1 |
Cooling Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C2 |
Telecom House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase I |
835836.2 |
815910.0 |
C4e |
Great Eagle Centre |
835932.8 |
815888.2 |
C4w |
Wan |
835629.8 |
815889.2 |
C5e |
Sun Hung Kai Centre (Eastern) |
836250.1 |
815932.2 |
C5w |
Sun Hung Kai Centre (Western) |
836248.1 |
815933.2 |
C6 |
Excelsior Hotel |
837009.6 |
815999.3 |
C7 |
|
837193.7 |
816150.0 |
C8 |
|
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
RC1 |
Proposed HKAPA Extension |
835487.7 |
815987.7 |
RC5 |
Sun Hung Kai Centre (Reprovision) |
836291.4 |
816029.7 |
RC7 |
|
837245.2 |
816156.6 |
Water Quality Parameters
4.3.4.
Monitoring of dissolved oxygen (DO), turbidity and
suspended solids (SS) shall be carried out at WSD flushing water intakes and
cooling water intakes. DO and Turbidity are measured in-situ while SS is
determined in laboratory.
4.3.5.
In association with the water quality parameters,
other relevant data shall also be measured, such as monitoring
location/position, time, sampling depth, water temperature, pH, salinity,
dissolved oxygen (DO) saturation, weather conditions, sea conditions, tidal
stage, and any special phenomena and work underway at the construction site
etc.
Sampling Procedures and
Monitoring Equipment
4.3.6.
The interval between two sets of monitoring should
not be less than 36 hours except where there are exceedances of Action and/or
Limit Levels, in which case the monitoring frequency will be increased. Table
4.5 shows the proposed monitoring frequency and water quality
parameters. Duplicate in-situ measurements and water sampling should be carried
out in each sampling event. For selection of tides for in-situ measurement and
water sampling, tidal range of individual flood and ebb tides should be not
less than 0.5m.
Table 4.5 Marine Water Quality Monitoring Frequency and
Parameters
Activities |
Monitoring Frequency1 |
Parameters2 |
During the 4-week
baseline monitoring period |
Three days per week, at
mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
During marine construction works |
Three days per week, at
mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
After completion of marine construction works |
Three days per week, at
mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
Notes:
1.
For selection of tides for in-situ measurement
and water sampling, tidal range of individual flood and ebb tides should be not
less than 0.5m.
2.
Turbidity should be measured in situ whereas SS
should be determined by laboratory.
Dissolved Oxygen and
Temperature Measuring Equipment
4.3.7.
The instrument should be a portable, weatherproof
dissolved oxygen measuring instrument complete with cable, sensor,
comprehensive operation manuals, and use a DC power source. It should be
capable of measuring:
¡P
a
dissolved oxygen level in the range of 0-20 mg/l and 0-200% saturation
¡P
a
temperature of 0-45 degree Celsius
4.3.8.
It should have a membrane electrode with automatic
temperature compensation complete with a cable. Sufficient stocks of spare
electrodes and cables should be available for replacement where necessary.
(e.g. YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with
reel and cable or an approved similar instrument).
4.3.9.
Should salinity compensation not be build-in in the
DO equipment, in-situ salinity shall be measured to calibrate the DO equipment
prior to each DO measurement.
Turbidity Measurement
Instrument
4.3.10.
The instrument should be a portable, weatherproof
turbidity-measuring instrument complete with comprehensive operation manual.
The equipment should use a DC power source. It should have a photoelectric
sensor capable of measuring turbidity between 0‑1000 NTU and be complete with a
cable (e.g. Hach model 2100P or an approved similar instrument).
Sampler
4.3.11.
A water sampler comprises a transparent PVC
cylinder, with a capacity of not less than 2 litres, and can be effectively sealed
with latex cups at both ends. The sampler should have a positive latching
system to keep it open and prevent premature closure until released by a
messenger when the sampler is at the selected water depth (e.g. Kahlsico Water
Sampler or an approved similar instrument).
Sample Container and
Storage
4.3.12.
Water samples for suspended solids measurement
should be collected in high-density polythene bottles, packed in ice (cooled to
4¢XC without being frozen), and delivered to ALS Technichem (HK) Pty Ltd. as soon
as possible after collection for analysis.
Water Depth Detector
4.3.13.
A portable, battery-operated echo sounder shall be
used for the determination of water depth at each designated monitoring
station. This unit can either be handheld or affixed to the bottom of the
workboat, if the same vessel is to be used throughout the monitoring programme.
Salinity
4.3.14.
A portable salinometer capable of measuring
salinity in the range of 0-40 ppt shall be provided for measuring salinity of
the water at each of monitoring location.
Monitoring Position
Equipment
4.3.15.
A hand-held or boat-fixed type digital Global
Positioning System (GPS) with waypoint bearing indication or other equivalent
instrument of similar accuracy shall be provided and used during monitoring to
ensure the monitoring vessel is at the correct location before taking
measurements.
Calibration of In-situ
Instruments
4.3.16.
All in-situ monitoring instrument shall be checked,
calibrated and certified by a laboratory accredited under HOKLAS or equivalent
before use, and subsequently re-calibrated at 3 monthly intervals throughout
all stages of the water quality monitoring. Responses of sensors and electrodes
should be checked with certified standard solutions before each use. Wet bulb
calibration for a DO meter shall be carried out before measurement at each
monitoring location.
4.3.17.
For the on site calibration of field equipment by
the ET, the BS 127:1993, "Guide to Field and on-site test methods for the
analysis of waters" should be observed.
4.3.18.
Sufficient stocks of spare parts should be
maintained for replacements when necessary. Backup monitoring equipment shall
also be made available so that monitoring can proceed uninterrupted even when
some equipment is under maintenance, calibration, etc.
4.3.19.
Current calibration certificates of equipments are
presented in Appendix
4.2.
Laboratory Measurement /
Analysis
4.3.20.
Analysis of suspended solids has been carried out
in a HOKLAS accredited laboratory, ALS Technichem (HK) Pty Ltd. Water samples of
about 1L shall be collected at the monitoring stations for carrying out the
laboratory SS determination. The SS determination work shall start within 24
hours after collection of the water samples. The SS determination shall follow
APHA 19ed or equivalent methods subject to the approval of IEC and EPD.
Enhanced Water
Quality Monitoring in the ex-Wan Chai Public Cargo
Working Area
and the
4.3.21.
The enhanced water quality monitoring and audit
programme is to avoid aggravation of odour nuisance from seawater arising from
temporary reclamation in the ex-Wan Chai Public Cargo Working Area and the
Causeway Bay Typhoon Shelter.
4.3.22.
Dissolved oxygen monitoring at the intakes C6 and
C7 in Causeway Bay Typhoon Shelter when there is temporary reclamation in
Causeway Bay Typhoon Shelter and at the south-western and south-eastern corners
of the ex-Wan Chai Public Cargo Working Area. The proposed water quality
monitoring stations of the Project are shown in Table 4.6 and Figure 4.1.
Table 4.6 Marine
Water Quality Stations for Enhanced Water Quality Monitoring
Station |
Location |
C6 |
Excelsior Hotel |
C7 |
|
Ex-WPCWA-SW |
South-western of
the ex-Wan Chai Public Cargo Working Area |
Ex-WPCWA-SE |
South-eastern of
the ex-Wan Chai Public Cargo Working Area |
4.3.23.
The monitoring of dissolved oxygen are to be
carried out 3 days per week, at mid-flood and mid-ebb tides for 3 water depths
(1m below water surface, mid-depth and 1m above sea bed, except where the water
depth less than 6m, the mid-depth may be omitted. If the water depth be equal
to or less than 3m, only the mid-depth will be monitored).
Daily SS
Monitoring and 24 hours Turbidity Monitoring System
4.3.24.
During dredging of the sediment at the
south-western corner of the Causeway Bay Typhoon Shelter, daily monitoring of suspended
solids and 24 hour monitoring of turbidity at the cooling water intakes (C6 and
C7) shall be conducted.
4.3.25.
The 24 hours monitoring of turbidty at the cooling water
intakes (C6 and C7) shall be established by setting up a continuous water quality
monitoring station in front of the intakes during the dredging activities. The
monitoring system include the turbidity sensor and data logger which is capable of data capturing at
every 5 minutes. The data sahll be downloaded daily and compared with the
Action and Limit level determined during the baseline water qualtiy monitoring
at the cooling water intake locations.
Additional Dissovled
oxygen Monitoring FOR CULVERT L WATER DISCHARGE FLOW
4.3.26.
In
response to the Condition 2.18 of the Environmental Permit no. EP-356/2009
requiring that a silt curtain / impermeable barrier system be installed to
channel water discharge flow from Culvert L to locations outside the embayment
area, a proposed replacement of the requirement with additional dissolved
oxygen monitoring has been conducted at three monitoring stations, namely A, B
and C between the eastern seawall of Central Reclamation Phase III and the
HKCEC Extension since November 2011 under EP-356/2009 so that DO level between
the eastern seawall of Central Reclamation Phase II and the HKCEC extension
could be continuously monitored.
4.3.27.
The proposed DO monitoring stations of the Project
are shown in Table 4.7 and Figure
4.1.
Table 4.7 Marine
Water Quality Stations for Additional DO Monitoring
Station |
Easting |
Northing |
A |
835468 |
815857 |
B |
835572 |
815961 |
C |
835659 |
816271 |
4.3.28.
The monitoring of dissolved oxygen are to be
carried out once per week, at mid-flood and mid-ebb tides for 3 water depths
(1m below water surface, mid-depth and 1m above sea bed, except where the water
depth less than 6m, the mid-depth may be omitted. If the water depth be equal
to or less than 3m, only the mid-depth will be monitored).
5.0.1.
The environmental monitoring will be implemented
based on the division of works areas of each designed project managed under
different contracts with separate FEP applied by individual contractors.
Overall layout showing work areas of various contracts, latest status of work
commencement and monitoring stations is shown in Figure
2.1 and Figure
4.1. The
monitoring results are presented in according to the Individual Contract(s).
5.0.2.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19 on 31 December 2011.
5.0.3.
The surrender of the Further Environmental Permit
for HY/2009/11 withdrew by contractor on 14 February 2012. However, there is no
work was conducted by the contractor.
5.0.4.
In the reporting month, the concurrent contracts
are as follows:
Contract no. HY/2009/11 Central - Wan Chai Bypass - North Point
Reclamation;
Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central-Wan
Chai Bypass at
Contract no. HK/2009/02 Wan Chai Development Phase II ¡V Central-Wan Chai
Bypass at Wan Chai East
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
Contract no. HK/2010/06 Wan Chai Development Phase II ¡V Central-Wan Chai
Bypass over MTR Tsuen Wan Line
Contract no. HY/2009/19- Cental- Wan Chai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link
5.0.5.
The environment monitoring schedules for reporting
month and coming month are presented in Appendix 5.1.
5.1.1.
Due to the equipment repair, the noise monitoring
at M4b and M6 were rescheduled from 23 August 2012 to 24 August 2012
Contract no. HY/2009/11 ¡V Central ¡V
Wanchai Bypass, North Point Reclamation
5.1.2.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19 on 31 December 2011
and the FEP-01/356/2009 was under application of surrender in this reporting
period. The monitoring was temporary suspended since 5 January 2012.
5.1.3.
The proposed division of noise monitoring stations
for Contract no. HY/2009/11 are summarized in Table 5.1 below:
Table 5.1 Noise
Monitoring Stations for Contract no. HY/2009/11
Station |
Description |
M4b |
Victoria Centre |
M5b |
|
5.1.4.
Day time and evening period noise monitoring was
conducted at the
5.1.5.
Noise monitoring results measured in this reporting
period are reviewed and summarized. No exceedance was recorded in reporting
month. Details of noise monitoring results and graphical presentation can be
referred in Appendix 5.2.
Contract no. HK/2009/01 - Wan Chai
Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC, Contract no.
HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
WanChai East and Contract no. HK/2010/06 Wan Chai Development Phase II ¡V
Central-Wan Chai Bypass over MTR Tsuen Wan Line
5.1.6.
The proposed division of noise monitoring stations
are summarized in Table 5.2 below.
Table 5.2 Noise
Monitoring Station for Contract nos. HK/2009/01, HK/2009/02 and HK/2010/06
Station |
Description |
M1a |
Harbour Road Sports Centre |
5.1.7.
Daytime and evening period noise monitoring was
conducted at the Harbour Road Sport Centre in the reporting month.
5.1.8.
No exceedance was recorded in this reporting
period. Details of noise monitoring results and graphical presentation can be
referred in Appendix 5.2
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
5.1.9.
The noise monitoring for HY/2009/15 was commenced
on 10 November 2010. The proposed division of noise monitoring stations are
summarized in Table 5.3 below.
Table 5.3 Noise
Monitoring Station for Contract no. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
5.1.10. Noise
monitoring results measured in the period of daytime and restricted hour are
reviewed and summarized. No exceedance was recorded in this reporting period. Details
of noise monitoring results and graphical presentation can be referred in Appendix 5.2
Contract no. HY/2009/19- Wan Chai
Bypass Tunnal (North Point Section) and Island Eastern Corridor Link
5.1.11.
The proposed division of noise monitoring stations
are summarized in Table 5.4 below.
Table 5.4 Noise
Monitoring Station for Contract no. HY/2009/19
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
5.1.12.
One limit level exceedance was recorded at M6 on 24
August 2012. The limit level exceedance was considered as non-project related. Details
of noise monitoring results and graphical presentation can be referred in Appendix 5.2
Contract no.
HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation and Contract no.
HY/2009/19 ¡V Central- Wan Chai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link
5.2.1.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19 on 31 December 2011
and the FEP-01/356/2009 was under application of surrender in this reporting
period.
5.2.2.
Real-time noise monitoring at FEHD Hong Kong
Transport Section Whitefield Depot commenced external wall renovation since 1
June 2012
Table 5.5 Real
Time Noise Monitoring Station for Contract no. HY/2009/11 and HY/2009/19
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD
Hong Kong Transport Section
Whitefield Depot |
North Point |
RTN2 |
Oil
Street Community Liaison
Centre |
* Real time noise
monitoring results and graphical presentation during night time period are for
information only.
5.2.3.
Exceedances were recorded at RTN2- Oil Street
Community Liaison Centre, between 0700 and 1900 hours throughout the reporting
month. Investigations found that no
major noisy activities by the Contractor HY/2009/19 were being performed. The
major noise impact was arising from the demolition works near
5.3.1.
Due to extension of site boundary by contractor of
HY/2009/19, location of air monitoring station CMA1b ¡V Oil Street Community
Liaison Centre has been finely adjusted on 21 April 2012.
5.3.2.
Due to lack of electricity supply, the 24-hr TSP
monitoring at the following stations were rescheduled:
CMA1b: from 27 Jul and 20 August 2012 to 31
Jul and 21 August 2012
CMA2a: from 27 Jul and 8 August 2012 to 28
Jul and 10 August 2012
CMA5a: from 20 August 2012 to 21 August 2012
CMA6a: from 8 August 2012 to 9 August 2012
5.3.3.
Due to adverse weather condition, the 1-hr TSP
monitoring at the following stations were rescheduled:
CMA2a: from 9 August 2012 to 11 August 2012
Contract no. HY/2009/11 ¡V Central ¡V
Wanchai Bypass, North Point Reclamation
5.3.4.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19 on 31 December
2011and the FEP-01/356/2009 was valid in this reporting period. The monitoring
for the contract was temporary suspended on 6 January 2012.
5.3.5.
The proposed division air monitoring stations is
summarized in Table 5.6 below.
Table 5.6 Air
Monitoring Stations for Contract no. HY/2009/11
Station |
Description |
CMA1b |
Oil Street Community Liaison Centre |
CMA2a |
|
5.3.6.
No exceedance was recorded in the reporting month.
Details of air monitoring results and graphical presentation can be referred in
Appendix
5.3.
Contract no. HK/2009/01 - Wan Chai
Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC
5.3.7.
Air monitoring was commenced on 1 April 2011 in
response to the commencement of the land-filling work for Contract no.
HK/2009/01. The proposed divisions of air monitoring stations are summarized in
Table 5.7 below. No exceedance was recorded in the reporting
month.
Table 5.7 Air
Monitoring Stations for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to |
CMA6a |
WDII PRE Site Office |
Contract no. HK/2009/02 - Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
5.3.8.
Air monitoring was commenced in mid-January 2011
for the land-filling work for Contract no. HK/2009/02. The proposed division of
air monitoring stations are summarized in Table 5.8 below. No
exceedance was recorded in the reporting month.
Table 5.8 Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
Contract
no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
5.3.9.
Air monitoring was commenced on 15 March 2011 for
the land filling work for Contract no. HY/2009/15. The proposed division of air
monitoring stations are summarized in Table 5.9 below. No
exceedance was recorded in the reporting month.
Table 5.9 Air
Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.3.10.
The odour patrol along the odour route with 7
sniffing locations was conducted by a qualified odour patrol member on 9 and 27
July 2012 at the concerned hours (afternoon for higher daily temperature). The
odour intensity detected at OP4 was found to be level 2 on 9 and 27 July 2012
which triggered Action Level. After investigation, the exceedances were likely
to be possible in relation to the sewage from outfall which was considered as
not work-related under the Project. The details of the odour patrol results and
meteorological conditions and on the date of odour patrol are shown in Appendix 5.3.
Contract
no. HY/2009/19- Wan Chai Bypass Tunnal (North Point Section) and Island Eastern
Corridor Link
5.3.11.
The proposed division of air monitoring stations
are summarized in Table 5.10 below. No exceedance was recorded in the reporting
month.
Table
5.10 Air Monitoring Stations for Contract
no. HY/2009/19
Station |
Description |
CMA1b |
Oil St Community
Liaison Centre |
CMA2a |
|
5.4.1.
Due
to the adverse weather condition (e.g. Amber Rainstorm signal or Strong wind
signal No.3 or above) were hoisted on 11 and 17 August 2012, water quality
monitoring at ebb tide were cancelled.
5.4.2.
WDII/RSS
advised that the dredging works for submarine pipeline at
5.4.3.
Based
on the joint inspection on 4 Jan 2012 for the NPR area, the 4-week water
quality monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9 to confirm no water
deterioration with respect to NPR was commenced since 7 Jan 2012 and it was
completed on 6 February 2012.
5.4.4.
Water
quality monitoring at WSD10 and WSD15 was temporary suspended while water
quality monitoring at WSD9 and WSD17 was implemented with respect to HK/2009/02
from 8 Feb 12 onwards;
5.4.5.
Water
quality monitoring at C8 and C9 have been implemented with respect to
HY/2009/19 since the marine bore piling work started on 28 Jan 12.
5.4.6.
Based
on the safety concern when external façade refurbishment was conducted by
contractor employed by Provident Centre (C9) since 3 Feb 2012, there is a fine
adjustment of the sampling location of water quality monitoring at C9 to the
closest accessible point prior to the completion of the external façade
refurbishment work.
5.4.7.
With respect to the trial dredging
at WCR2 was scheduled on 20, 22, 24, 25 March and 1, 3 ,
11, 13, 15, 17, 19, 20 Apr and
3 May 2012, on-going water quality monitoring results at WSD21 during
this period was checked and indicated that there was no contribution due to the
trial dredging operation. Enhanced review of water quality around WCR2
was also implemented and no deterioration in the water quality was observed.
5.4.8.
Due to the access of water
monitoring station at WSD19 was blocked by LCSD construction works from 3 April
2012 to 2 May 2012 and lead to the inaccessibility of sampling either land and
marine, there is a fine adjustment of the sampling point of WSD 19 since 5
April 2012 to the closest accessible point prior to the completion of the
construction activities.
5.4.9.
Due to the dredging works for
Cross Harbour Water Mains from Wan Chai to Tsim Sha Tsui- DP6 was completed on
26 March 2012, the temporary suspension of impact water quality monitoring at
WSD7 and WSD20 after 27 April 2012 for the water quality monitoring at WSD7 and
WSD20 have been monitored for 4-week period after the completion of DP6 to
confirm no water deterioration.
5.4.10. During the weekly site inspection for
HY/2009/15 on 10 July 2012 and further inspection on 11 July 2012, it was found
that the seawall blocks on the south side of TCBR1E (TS1) have been removed
before all dredging works have been completed. The contractor has immediately
surrounded the seawall gap with silt curtains and stopped the relevant dredging
works on 12 July 2012. No action or
limit level exceedance was found during the water quality monitoring on 9 or 11
July 2012. The contractor has
promised to provide double layer silt curtains and geotextile to act as
temporary seawall and covered the sloping seawall with geotextile, and would
provide a full incident report. A
self water quality monitoring was conducted on 15 July 2012 to indicate the
effectiveness of the double silt curtain layers and would perform each time
during dredging operations. The
results from the self water quality monitoring showed that the suspended
solids, turbidity and dissolved oxygen level outside the double silt curtain
layers were not affected by the dredging activities inside the silt curtain
layers.
Contract no. HY/2009/11 ¡V Central ¡V
Wanchai Bypass, North Point Reclamation
5.4.11.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19 on 31 December 2011
and the FEP-01/356/2009 was valid in this reporting period.
5.4.12.
The proposed division of water monitoring stations
for Contract no. HY/2009/11 are summarized in Table 5.11 below:
Table 5.11 Water Monitoring Stations for Contract no. HY/2009/11
Station
Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
|
839790.3 |
817032.2 |
Cooling Water Intake |
|||
C8 |
|
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
Remarks:
WSD9, WSD10, WSD15, WSD17, C8 and C9 water monitoring finished on 6 Feb 2012.
Contract no. HK/2009/01 - Wan Chai
Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC
5.4.13.
Water monitoring for Contract no. HK/2009/01 was
commenced on 23 July 2010. The proposed division of water monitoring stations
are summarized in Table 5.12 below.
Table 5.12 Water Monitoring Stations for Contract no. HK/2009/01
Station
Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD7 |
|
834150.0 |
818300.3 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
|
830750.6 |
816030.3 |
Cooling Water Intake |
|||
C1 |
HKCEC
Extension |
835885.6 |
816223.0 |
C2 |
Telecom
House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase
I |
835836.2 |
815910.0 |
C4e |
Great Eagle
Centre |
835932.8 |
815888.2 |
C4w |
Wan |
835629.8 |
815889.2 |
Remarks:
- The
water monitoring stations for the dredging works under Contract No. HK/2009/01
should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at
these locations have not been carried out by others. Similarly, the water
monitoring stations for the dredging works under Contract No. HK/2009/02 should
also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations have not been carried out by others.
- WSD7 and WSD20 water quality
monitoring were temporarily suspended since 27 Apr 2012.
Contract no. HK/2009/02 - Wan Chai
Development Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
WanChai East
5.4.14.
Water monitoring for Contract no. HK/2009/02 was
commenced on 8 July 2010. The proposed division of water monitoring stations
are summarized in Table 5.13 below.
Table 5.13 Water Monitoring Stations for
Contract no. HK/2009/02
Station
Ref. |
Location |
Easting |
Northing |
|||
WSD Salt Water Intake |
||||||
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
|||
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
|||
WSD17 |
|
839790.3 |
817032.2 |
|||
Cooling Water Intake |
||||||
C5e |
Sun Hung Kai
Centre (Eastern) |
836250.1 |
815932.2 |
|||
C5w |
Sun Hung Kai
Centre (Western) |
836248.1 |
815933.2 |
|||
Remarks:
-
The
water monitoring stations for the dredging works under Contract No. HK/2009/01
should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at
these locations have not been carried out by others. Similarly, the water
monitoring stations for the dredging works under Contract No. HK/2009/02 should
also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations has not been carried out by others.
-
Water
quality monitoring at WSD9 and WSD 17 was implemented with respect to
HK/2009/02 from 8 Feb 2012.
Contract no. HK/2010/06
- Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan
Line
5.4.15.
Water monitoring for Contract no. HK/2010/06 was
commenced on 8 March 2011. The proposed division of water monitoring stations
are summarized in Table 5.14 below.
Table 5.14 Water Monitoring Stations for Contract no. HK/2010/06
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C2 |
Telecom
House |
835647.9 |
815864.4 |
Contract
no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
5.4.16.
Due to the commencement of the maintenance dredging
on 10 November 2010, water quality monitoring for Contract no. HY/2009/15 was
commenced on 9 November 2010. The proposed division of water monitoring
stations are summarized in Table 5.15 below.
Table 5.15 Water Monitoring Stations for
Contract no. HY/2009/15
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C6 |
Excelsior Hotel |
837009.6 |
815999.3 |
C7 |
|
837193.7 |
816150.0 |
Remarks: - The cessation of seawater intake
operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was
then terminated since 17 May 2011.
Contract no. HY/2009/19 ¡V Central- Wan
Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
5.4.17.
Due to the commencement of the marine bored piling
on 28 Jan 2012, water quality monitoring for Contract no. HY/2009/19 was
commenced on 28 Jan 2012. The proposed division of water monitoring stations
are summarized in Table 5.16 below.
Table 5.16 Water Monitoring Stations for Contract no. HY/2009/19
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C8 |
|
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
Remarks: C8 and C9 monitoring commenced on 28 Jan 2012.
5.4.18. Based on the safety concern when external
façade refurbishment was conducted by contractor employed by Provident Center
(C9) between 9 January 2012 to 30 July 2012 which caused to the inaccessibility
of sampling either land and marine since 3 Feb 2012, there is a fine adjustment
of the sampling location of water quality monitoring at C9 since 10 March 2012
to the closest accessible point prior to the completion of the external façade
refurbishment work.
5.4.19. Due to the access of water monitoring
station at WSD19 was blocked by LCSD construction works from 3 April 2012 to 2
May 2012 and lead to the inaccessibility of sampling either land and marine,
there is a fine adjustment of the sampling point of WSD 19 since 5 April 2012
to the closest accessible point prior to the completion of the construction activities.
5.4.20. As per the meeting with the
representative of Excelsior Hotel and World Trade Centre on 17 May 2011, they
confirmed that the seawater intake for The Excelsior was no longer in use and
replaced by the connected permanent water supply from WSD pipelines since 11
January 2011. Thus, the impact water quality monitoring for the cooling intake
- C6 was terminated effective from 26 May 2011.
5.4.21. 24 hours monitoring of turbidity at the cooling water intakes at
C7 was conducted. With respect to the seawall collapsing
at TS4 on 17 November 2011, the 24 hours turbidity monitoring and was kept in
November 2011. Since the reinstating
the seawall was completed on 13 January 2012 and no any water deterioration was
performed, 24 hour turbidity monitoring was then suspended on 27 January 2012.
5.4.22.
Water monitoring results measured in this reporting
period are reviewed and summarized. Details of water quality monitoring results and
graphical presentation can be referred in Appendix 5.4.
Table 5.17 Summary
of Water Quality Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
|||||||||
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|||
HY/2009/11 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring finished
on 6 Feb 2012 |
WSD10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD15 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C8 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/01 |
WSD19 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C3 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C4e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C4w |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring finished
on 27 April 2012 |
WSD20 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
HK/2009/01 & HK/2010/06 |
C2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C5w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
1 |
|
Monitoring started
on 8 Feb 2012 |
WSD21 |
0 |
0 |
0 |
0 |
2 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
|
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HY/2009/15 |
C7 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HY/2009/19 Monitoring started on 28 Jan 2012 |
C8 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
1 |
|
C9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
Total |
2 |
0 |
0 |
0 |
4 |
0 |
1 |
0 |
0 |
2 |
2 |
2 |
||
Remarks:
- The cessation of seawater intake operation for
C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated
since 17 May 2011.
-
WSD9 and WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.
-
4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9
were completed on 6 Feb 2012.
- C8 and C9 were
implemented with respect to HY/2009/19 from 28 Jan 2012.
- WSD7 and WSD20 were
temporarily suspended from 27 Apr 2012
5.4.23. Enhanced DO monitoring at 4 monitoring
stations in Causeway Bay Typhoon Shelter and Ex-Public Cargo Works Area was
conducted three days per week during the reporting period. The action and limit
level exceedances of water quality monitoring are summarized in Table 5.18.
Table 5.18 Summary of Enhanced Dissolved Oxygen Monitoring
Exceedances in Reporting Month
Contract
no. |
Water
Monitoring Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
|
LL |
|
LL |
||
HY/2009/15 |
C6 |
0 |
0 |
0 |
0 |
C7 |
2 |
0 |
0 |
0 |
|
Ex-WPCWA SW |
0 |
0 |
0 |
4 |
|
Ex-WPCWA SE |
5 |
0 |
4 |
3 |
|
Total |
7 |
0 |
4 |
7 |
5.4.24.
There were 11 action
level exceedances and 7 limit level exceedances recorded in enhanced dissolved oxygen monitoring
in this reporting period.
5.4.25. In response to the Condition 2.18 of
the Environmental Permit no. EP-356/2009 requiring that a silt curtain /
impermeable barrier system be installed to channel water discharge flow from
Culvert L to locations outside the embayment area, a proposed replacement of
the requirement with additional dissolved oxygen monitoring has been conducted
at three monitoring stations, namely A, B and C between the eastern seawall of
Central Reclamation Phase III and the HKCEC Extension since November 2011 under
EP-356/2009 so that DO level between the eastern seawall of Central Reclamation
Phase II and the HKCEC extension could be continuously monitored. Details of additional DO monitoring results can be
referred in Appendix 5.4a.
Contract no. HY/2009/11 ¡V Central ¡V
Wanchai Bypass, North Point Reclamation
5.5.1.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. Therefore,
no C&D waste was generated.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
5.5.2.
Inert and non- inert C&D waste were disposed of
in this reporting month. Details of the waste flow table are summarized in Table
5.19.
Table 5.19 Details
of Waste Disposal for Contract no. HK/2009/01
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
22.035 |
22245.415 |
TKO137, TM38 |
Inert C&D materials recycled, m3 |
355 |
4979.5 |
N/A |
Non-inert C&D materials disposed, m3 |
57.1 |
942.88 |
|
Non-inert C&D materials recycled, kg |
483 |
151143 |
N/A |
Chemical waste disposed, kg |
150 |
7200 |
N/A |
*Marine Sediment (Type 1 ¡V Open Sea Disposal), m3 |
0 (Bulk Volume) |
91164.2 (Bulk Volume) |
South of Cheung Chau |
* Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites)
& Type 2 ¡V Confined Marine Disposal) , m3 |
0 (Bulk Volume) |
43018 (Bulk Volume) |
East of Cha Chau |
Dredged Sediment Requiring Type 3
¡V Special Treatment / Disposal contained in Geosynthetic Containers |
0 (Bulk Volume) |
5613 (Bulk Volume) |
East of Cha Chau |
Remarks: Contractor clarified and updated waste flow table for the
reporting month of August
5.5.3.
There were no marine sediments Type 1 ¡V Open Sea Disposal (Dedicate
Sites) & Type 2 ¡V Confined Marine Disposal disposed in the reporting month.
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
5.5.4.
Inert and non- inert C&D waste were disposed of
in this reporting month. Details of the waste flow table are summarized in Table
5.20.
Table 5.20 Details
of Waste Disposal for Contract no. HK/2009/02
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
1345 |
174298 |
TKO137 / TM 38 |
Inert C&D materials recycled, m3 |
18161 |
18161 |
N/A |
Non-inert C&D materials disposed, m3 |
48 |
586 |
SENT Landfill |
Non-inert C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Chemical waste disposed, kg |
NIL |
4721 |
N/A |
Marine Sediment (Type 1 ¡V Open Sea Disposal), m3 |
NIL |
154,827 (Bulk volume) |
South of Cheung Chau |
Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites)
& Type 2 ¡V Confined Marine Disposal) , m3 |
Nil |
114464 (Bulk volume) |
East of Sha Chau |
5.5.5.
There were no marine sediments Type 1 ¡V Open Sea Disposal (Dedicate
Sites) & Type 2 ¡V Confined Marine Disposal disposed in the reporting month.
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V
Tunnel (
5.5.6.
No inert and non- inert C&D waste were disposed
of in this reporting month. Details of the waste flow table are summarized in Table
5.21
Table 5.21 Details
of Waste Disposal for Contract no. HY/2009/15
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
141579.2 |
Tuen Mun Area 38 |
NIL |
65216 |
TKO137 FB |
|
Inert C&D materials recycled, m3 |
NIL |
184.0 |
To Contract HY/2009/11 |
NIL |
304 |
ex-PCWA |
|
NIL |
111.9 |
TS4 |
|
Non-inert C&D materials disposed, m3 |
NIL |
252.2 |
SENT Landfill |
Non-inert C&D materials recycled, kg |
NIL |
299361.5 |
N/A |
Chemical waste disposed, kg |
NIL |
8,200 |
N/A |
Marine Sediment (Type 1 ¡V Open Sea Disposal),
m3 |
16,775 |
96,877 (Bulk Volume) |
South of Cheung Chau |
Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) &
Type 2 ¡V Confined Marine Disposal) , m3 |
7,970 |
207,285 (Bulk Volume) |
East of Sha Chau |
Marine
Sediment (Type 3 ¡V Special Treatment / Disposal contained in Geosynthetic
Containers) |
NIL |
7,050 (Bulk Volume) |
East of Sha Chau |
There were marine sediments Type 1- Open Sea
Disposal, Type
1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal dredging from
bore-piling casing in the reporting month.
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
5.5.7.
Inert C&D waste was recycled of in this
reporting month. Details of the waste flow table are summarized in Table
5.22.
Table 5.22 Details
of Waste Disposal for Contract no. HK/2010/06
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
0 |
11027.83 |
TM38 |
Inert C&D materials recycled, m3 |
266.8 |
266.8 |
HK/2009/01 |
Non-inert C&D materials disposed, m3 |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled, kg |
0 |
1374.5 |
N/A |
Chemical waste disposed, L |
0 |
600 |
N/A |
Marine Sediment (Type 1 ¡V Open Sea Disposal), m3 |
0 (Bulk Volume) |
3,694 (Bulk Volume) |
South Cheung Chau |
Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) &
Type 2 ¡V Confined Marine Disposal) , m3 |
0 (Bulk Volume) |
12,297 (Bulk Volume) |
|
There were no marine
sediments Type 1 ¡V Open Sea
Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal dredging from
bore-piling casing in the reporting month.
Contract no. HY/2009/19 ¡VCentral- WanChai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
Table 5.23 Details of Waste Disposal for
Contract no. HY/2009/19
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
17610.48 |
36585.7 |
TM38 |
Inert C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed, m3 |
30.75 |
55.97 |
N/A |
Non-inert C&D materials recycled, kg |
NIL |
NIL |
N/A |
Chemical waste disposed, L |
NIL |
0.29 |
N/A |
Marine Sediment (Type 1 ¡V Open Sea Disposal), m3 |
NIL |
NIL |
South Cheung Chau |
Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) &
Type 2 ¡V Confined Marine Disposal) , m3 |
NIL |
105 |
|
There was no marine sediment (Type 1- Open sea
disposal) disposed of in this reporting month.
6.0.1.
The Event Action Plan for construction noise, air
quality and water quality are presented in Appendix 6.1.
Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point
Reclamation
6.1.1
No exceedance was recorded in the reporting month.
Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central
¡VWanchai Bypass at HKCEC
6.1.2
No exceedance was recorded in the reporting month.
Contract no.
HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai
East
6.1.3
No exceedance was recorded in the reporting month.
Contract no.
HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
6.1.4
No exceedance was recorded in the reporting month.
Contract no.
HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over MTR
Tsuen Wan Line
6.1.5
No exceedance was recorded in the reporting month.
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
6.2.1
Exceedances were recorded between 0700 and 1900
hours throughout the reporting month. Investigation found that no major noisy
activities by Contractor HY/2009/19 were being performed. The major noise
impact was arising from the demolition works near Oil Street Community Liaison Centre.
As such, the exceedances were concluded as not project related.
6.3.1.
No exceedance was recorded in 1-hr TSP and 24-hrs
TSP monitoring in the reporting month.
6.3.2.
No exceedance was recorded in Odour patrol
monitoring in the reporting month.
Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point
Reclamation
6.4.1
No exceedance was recorded in the reporting month.
Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central
¡VWanchai Bypass at HKCEC
6.4.2
SS exceedances at C3 were recorded on 6 August 2012
in this reporting month. Confirmed with Contractor, there was no work conducted
on that day. The exceedances were possible in relation to the natural variation
or changes of water quality and considered not related to project.
6.4.3
SS exceedance at WSD19 was recorded on 25 August
2012. Checking with contractor¡¦s work, rock filling inside the water channel
was conducted on that day. In view that there was no exceedance at the
monitoring stations within site area and the silt screen was in proper
condition. The exceedance was considered non-project related.
6.4.4
DO exceedance at C4w was recorded on 20 August
2012. No odour nuisance was detected during DO monitoring. Checking
with Contractor¡¦s work, there was no work conducted on that day. The exceedance
was possible in relation to the natural variation or changes of water quality
and considered not related to project.
Contract no.
HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
WanChai East
6.4.5
There were SS and Turbidity exceedances at mid-ebb
recorded at C5w on 30 July 2012. After checking with Contractor, filling in
WCR2 and substructure works for the New Ferry Pier were conducted on that day.
Reviewing the results at the monitoring stations nearer than C5w, no exceedance
was recorded. The exceedance was possible due to the materials from the
cleaning screen panel at SHK unavoidably collected during monitoring.
6.4.6
There were SS exceedances at mid-flood recorded at WSD21
on 4 August 2012. After checking with Contractor, filling in WCR2 and
substructure works for the New Ferry Pier were conducted on that day. Reviewing
the results at the monitoring stations nearer than WSD21, no exceedance was
recorded. The exceedance was possible due to the materials from the cleaning
screen panel at Wan Chai WSD Pumping station unavoidably collected during
monitoring.
6.4.7
There were occasionally SS exceedances recorded at
WSD21 in this reporting month. No odour nuisance was noted during DO monitoring.
Checking with Contractor¡¦s work, filling at WCR2 was conducted on these days.
Reviewing the results at the monitoring stations within site area, no
exceedance was recorded. The exceedances were possible in relation natural
variation or changes of water quality in the vicinity of the water quality
monitoring station and the exceedances considered not related to project.
Contract no.
HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
6.4.8
There was DO exceedance at C7 recorded on 28 July
2012. After checking with Contractor, the deployed silt screen at intake and
silt curtain were observed to be in proper condition for TS1 removal work and
TS2 dredging. Accumulation of floating debris near monitoring station was
observed. The exceedance was possibly related to the accumulation of floating
debris near monitoring station. Contractor was reminded the water quality near
to the intake should be provided sufficient inspection and prevents the
accumulation of floating debris. The exceedance was considered not related to
the project works.
6.4.9
There were occasionally DO exceedances at Ex-WPCWA
SE and Ex-WPCWA SW recorded in this reporting month. No odour nuisance was
noted during DO monitoring. After checking with Contractor, there was no marine
work undertaken at ex-WPCWA. The exceedances were possible in relation to the
accumulation of organic particles discharge from culvert near monitoring
station and considered not related to
the Projects works.
Contract no.
HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over MTR
Tsuen Wan Line
6.4.10 No exceedance
was recorded in this reporting month.
Contract no.
HY/2009/19- Central- Wan Chai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link
6.4.11 There were
occasionally SS and turbidity exceedances at C8 recorded in this reporting
month. Confirmed with Contractor, there was no marine work conducted near C8.The
exceedances were possible in relation to the accumulation of particles
discharged from outfalls near monitoring stations and not related to project.
6.4.12 Summary for
notification of exceedances can be referred to Appendix 6.2.
6.5.1.
During the reporting month of August 2012,
contractor of HY/2009/15 has failed to demonstrate compliance with the conditions
set in FEP-04/356/2009 and relevant conditions in EP-356/2009 for the temporary
reclamation removal operations at TCBR1E (TS1). Contractor was unable to provide a proper
method statement with respect to the change in works circumstance, and the
Contractor was unable to effectively mitigate the impact due to non-compliance
such that muddy boom recurrence
occurred and dispersed into
6.5.2.
The observations and recommendations from site
audits made in each individual site audit session were presented in Section 8.
6.6.1.
Warning letters from ETL regarding the situation at
TS1 were issued to the contractor of HY/2009/15 on multiple occasions with
recommended mitigation measures, and the contractor has immediately deployed
silt curtains to conceal the seawall gaps.
6.6.2.
As removal dredging and barge mooring operations
were anticipated to be performed at the southern side of TS1, ETL requested
that daily self water quality tests during removal dredging operations, also
pilot test for mooring operations, to demonstrate the effectiveness of the
mitigation measures during the operation and to demonstrate the operation
itself would not cause substantial water quality impact, should be performed
before the mooring operations.
These tests were requested to prove whether conditions set in
FEP-04/356/2009 and relevant conditions EP-356/2009 are fully complied.
6.6.3.
Water samplings for self water quality tests were
collected at locations inside and outside the silt curtains during removal
dredging operations. This was to
demonstrate whether the double silt curtains could
effectively hold back silty water during removal dredging operations.
6.6.4.
Water samplings for pilot test were collected
inside and outside the double silt curtains before and after the mooring
operations. This was to demonstrate
whether the double silt curtains could effectively hold back silty water during
removal mooring operations, and if high turbid would be generated during the
mooring operations.
6.6.5.
On 15 July 2012, a successful self water quality
test was performed by the contractor.
6.6.6.
Pilot tests were carried out on 27 July, 2, 7 and
20 Aug 2012 to demonstrate the compliance of barge mooring operations with the
conditions set in FEP-04/356/2009 and EP-356/2009, but none of the pilot test
was successful.
6.6.7.
It is concluded that the self water quality tests
proved the effectiveness of the mitigation measures, but the pilot tests were a
failure and the contractor cannot demonstrate their ability to comply with the
conditions set in FEP-04/356/2009 and EP-356/2009.
6.6.8.
ETL then strongly recommended the Contractor to
follow the following points for future activities. First, the Contractor should request for
RSS inspections for confirmation of implementation of mitigation measures
before any commencement of work activities that are governed by the EP. Second, if there is any site mitigation
measure not confirmed by RSS for fulfilling the agreed method statements,
contractor shall not commence any environmentally sensitive construction
activities (e.g. dredging, filling, mooring or any works related to temporary
reclamation) unless such site mitigation measures have been properly reviewed
by both ET and IEC. Third, the
revised site mitigation measures should be reviewed and consented by both ET
and IEC before implementation.
6.6.9.
The Contractor and RSS agreed on the above points
and the Contractor submitted Investigation Report regarding the incident at TS1,
Rectification Plan, Preventive Action Plan and revised Method Statement on 7 September
2012.
7.0.1.
According to Condition 3.4 of the EP-356/2009, this
section addresses the relevant cumulative construction impact due to the
concurrent activities of the current projects including the Central Reclamation
Phase III, Central-Wanchai Bypass and Island Eastern Corridor Link projects.
7.0.2.
According to the Monthly EM&A report (July
2012) of Central Reclamation Phase III (CRIII), filling works, building
construction works and pipe works were performed in the July 2012 reporting
month. The water quality monitoring was completed in October 2011 and no exceedance
was recorded for air and noise monitoring. It can be concluded that cumulative construction
impact due to the concurrent activities of the current projects with the
Central Reclamation Phase III (CRIII) was insignificant.
7.0.3.
According to the construction programme of Wan Chai
Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link
projects, the major construction activities at Reclamation Shoreline Sub-zones
under Wan Chai Development Phase II were the dredging and filling at HKCEC3w,
dredging at submarine sewage pipelines, reinstatement of seawall block
construction at TCBR1W and marine bored piling at MTR Tunnel Crossing in the
reporting month. The major environmental impact was water quality impact at,
7.0.4.
The major environmental impacts generated from the reclamation
work at Central Reclamation Phase III were only located along the coastline of
Central and Admiralty. As no project related exceedance was recorded in the
Project, it was considered no adverse environmental impact caused by the
Project works. Thus, it is evaluated the cumulative construction impact was
insignificant.
8.0.1.
During this reporting month, weekly environmental
site audits were conducted for Contracts no. HK/2009/01, HK/2009/02, HY/2009/15,
HK/2010/06 and HY/2009/19. No non-conformance was identified during the site
audits.
8.0.2.
Four site inspections for Contract no. HK/2009/01
were carried out on 1, 8, 16 and 22 August 2012 in reporting month. Results of these inspections
and outcomes are summarized in Table 8.1.
Table 8.1 Summary
of Environmental Inspections for Contract no. HK/2009/01
Item |
Date |
Observations |
Action taken by
Contractor |
Outcome |
120801_01 |
1-Aug-12 |
The condition of tree protection fences for trees (T608, 061)
should be improved (TST) |
The tree protection fences condition was improved. |
Completion as observed on 8-Aug-12 |
120801_02 |
1-Aug-12 |
The oil stain was observed on the ground which should be removed
and disposed as chemical waste. (VIP area, Water Channel) |
The oil stain was removed |
Completion as observed on 8-Aug-12 |
120808_01 |
8-Aug-12 |
Watering during breaking should be provided for dust suppression |
Watering during breaking should be provided for dust suppression |
Completion as observed on 16-Aug-12 |
120816_01 |
16-Aug-12 |
Drip tray should be provided for chemical containers (VIP area) |
Drip tray should be provided for chemical containers (VIP area) |
Completion as observed on 22-Aug-12 |
8.0.3.
Four site inspections for Contract no.
HK/2009/02 were carried out on 2, 9, 15 and 22 August 2012 during this reporting
period. The results of these inspections and outcomes are summarized in Table
8.2.
Table 8.2 Summary
of Environmental Inspections for Contract no. HK/2009/02
Item |
Date |
Observations |
Action taken by
Contractor |
Outcome |
120802_01 |
2-Aug-12 |
The seepage of muddy water from the sheet pile was observed.
Better protection should be provided to prevent seepage and the silt curtain
should be deployed for protection. (Eastern sheetpile) |
Silt curtain was provided. |
Completion as observed on 9-Aug-12 |
120815_01 |
15-Aug-12 |
The tarpaulin sheet should be provided for the transfer of
sediment to barge. (WCR1) |
The tarpaulin sheet was provided. |
Completion as observed on 22-Aug-12 |
120815_02 |
15-Aug-12 |
The condition of temporary drainage system should be improved to
ensure its efficiency. (Gate 2) |
The condition of temporary drainage system was improved. |
Completion as observed on 22-Aug-12 |
120822_01 |
22-Aug-12 |
The stockpile should be covered by tarpaulin sheet (Next to SPCA,
Small ex-pet garden) |
The stockpile was removed, |
Completion as observed on 30-Aug-12 |
120822_02 |
22-Aug-12 |
The maintenance of the U-channel should be improved and the sand
bags should be provided to prevent surface runoff. (small ex-pet garden) |
The condition of U-channel was improved. |
Completion as observed on 30-Aug-12 |
8.0.4.
Four site inspections for Contract no. HY/2009/15 were
carried out on
31 July, 7, 14 and 21 August 2012 in reporting month. The results of
these inspections and outcomes are summarized in Table 8.3.
Table 8.3 Summary
of Environmental Inspections for Contract no. HY/2009/15
Date |
Observations |
Action taken by
Contractor |
Outcome |
|
120731_01 |
31-Jul-12 |
The oil was observed on the water which should
be removed and treated (TS1) |
Oil stains were being removed as chemical waste
treatment. |
Completion as observed
on 21-Aug-12 |
120807_01 |
7-Aug-12 |
Better maintenance of marine vessels to avoid
oil leakage (TS1). |
Marine vessels were maintained to avoid oil
leakage. |
Completion as observed
on 14-Aug-12 |
120807_02 |
7-Aug-12 |
Better maintenance of silt curtains to avoid
holes and gaps (TS1). |
New silt curtains were deployed |
Completion as observed
on 14-Aug-12 |
120807_03 |
7-Aug-12 |
Oil leakage on ground should be removed (TS4). |
Oil leakage was cleared as chemical waste. |
Completion as observed
on 14-Aug-12 |
120807_04 |
7-Aug-12 |
Haul roads should be kept wet (TS4) |
Water spraying on haul roads to keep the haul
road wet. |
Completion as observed
on 14-Aug-12 |
120807_05 |
7-Aug-12 |
Muddy water was observed to be running into
public manhole. Contractor
should take actions to prevent runoff. (Gate of TS4/ME4) |
Better maintenance of wheel wash area to avoid
runoff. |
Completion as observed
on 14-Aug-12 |
120807_06 |
7-Aug-12 |
Three side cover of grouting machine should be
maintained to ensure three sides and top are covered (TPCWAE) |
The grouting machine was no longer in use and
three sides and top cover is provided for the new grouting machine. |
Completion as observed
on 14-Aug-12 |
120807_07 |
7-Aug-12 |
Chemical drums should be stored in approiate
area (TPCWAE). |
Drip trays were provided for chemical drums. |
Completion as observed
on 14-Aug-12 |
120807_08 |
7-Aug-12 |
Floating refuse should be collected more
regularly |
Floating refuse at TS1 and SW corner were
collected |
Completion as observed
on 14-Aug-12 |
120814_01 |
14-Aug-12 |
The northern seawall has been removed to below
high water mark, and muddy boom is observed going into the |
Impermable barriers were deployed to cover
sloping seawall |
Completions as observed
on 21-Aug-12 |
120814_02 |
14-Aug-12 |
Chemical waste and wastewater should be cleared
from drip trays (TS1) |
Chemical waste and wastewater were removed. |
Completions as observed
on 21-Aug-12 |
120814_03 |
14-Aug-12 |
Oil leakage should be cleared as chemical waste
(TS4 and TPCWAE) |
Oil leakage was cleared as chemical waste. |
Completions as observed
on 21-Aug-12 |
120814_04 |
14-Aug-12 |
Floating refuse should be collected (Western
side of TPCWAE (landing steps)) |
Floating refuse was collected |
Completions as observed
on 21-Aug-12 |
120821_01 |
21-Aug-12 |
TS4 - Site drainage system shall be cleaned
regularly and properly maintained such that it could be adequate to handle
the runoff capacity. |
Drainage channels were cleared of mud. |
Completion as observed
on 28-Aug-12 |
120821_02 |
21-Aug-12 |
TS4 - Site drainage layout plan and measures
shall be reviewed and updated to tally with the discharge license
requirement. |
Updated drainage plan was provided that tally
with the discharge license requirement. |
Completion as observed
on 28-Aug-12 |
120821_03 |
21-Aug-12 |
Impermeable barrier were observed inadequate to
protect the removed seawall location requiring further trimming/dredging at
TS1. |
More silt curtains and impermeable barriers
were provided at TS1. |
Completion as observed
on 28-Aug-12 |
120821_04 |
21-Aug-12 |
Inadequate silt curtain were observed for
protecting trimming work at breakwater at TS1. |
More silt curtains and impermeable barriers
were provided at TS1. |
Completion as observed
on 28-Aug-12 |
8.0.5.
Five site
inspections for Contract no. HK/2010/06 was carried out on 30 July, 7, 16, 20 and 27 August 2012 in reporting month. The results of
these inspections and outcomes are summarized in Table 8.4.
Table 8.4 Summary
of Environmental Inspections for Contract no. HK/2010/06
Item |
Date |
Observations |
Action taken by
Contractor |
Outcome |
120730_01 |
30-Jul-12 |
The floating debris should be removed
regularly. (2w) |
The floating debris should be cleaned regularly |
Completion as observed
on 7-August-12 |
120730_02 |
30-Jul-12 |
Chemical containers should be provided with
drip tray or store into the designated storage area (2w) |
Chemical containers were removed. |
Completion as observed
on 7-August-12 |
120807_01 |
7-Aug-12 |
Better protection should be provided at the
edge of the platform to prevent surface runoff (2w) |
The protection was provided |
Completion as observed
on 16-August-12 |
120807_02 |
7-Aug-12 |
The split was observed in U-channel which
should be repaired immediately (2e) |
The U-channel was repaired |
Completion as observed
on 16-August-12 |
120816_01 |
16-Aug-12 |
The oil stain was observed on the platform
which should be removed and disposed as chemical waste (2w) |
The oil stain was removed as chemical waste. |
Completion as observed
on 20-August-12 |
120816_02 |
16-Aug-12 |
The condition and the silt accumulated in
U-channel should be improved and removed (2e) |
The condition of U-channel was improved. |
Completion as observed
on 20-August-12 |
120816_03 |
16-Aug-12 |
Drip tray should be provided for oil drums (2w) |
The oil drums were removed. |
Completion as observed
on 20-August-12 |
120820_01 |
20-Aug-12 |
The overflow of temporary sedimentation tank
was observed. The contractor should review the adequacy of the sedimentation
tank and provide the sand bags around the edge of the platform to prevent
surface runoff (2w) |
The temporary sedimentation tank was removed. |
Completion as observed
on 27-August-12 |
120820_02 |
20-Aug-12 |
The filter for oil intercepter should be
replaced (2w) |
The filter was
cleaned. |
Completion as observed
on 3-September-12 |
120827_01 |
27-Aug-12 |
The condition of U-channel should be improved
(2w) |
The condition of U-channel was improved. |
Completion as observed
on 3-September-12 |
8.0.6.
Four site
inspections for Contract no. HY/2009/19 were carried out on 1, 8, 15 and 23 August 2012 in reporting month. The results of these
inspections and outcomes are summarized in Table 8.5.
Table 8.5 Summary
of Environmental Inspections for Contract no. HY/2009/19
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
120823_01 |
23-Aug-12 |
Overflow into sea from drainage channel was
observed at ferry pier 2, the contractor is strongly recommended to provide
adequate measures to ensure the site drainage is adequate. |
Measures were provided to improve site
drainage. |
Completion as observed
on 30-Aug-12 |
120823_02 |
23-Aug-12 |
Multiple oil stains were observed at Portion
VII, the contractor should removed the oil stains as chemical waste and
identify and treat at source. |
The oil stain was removed. |
Completion as observed
on 30-Aug-12 |
9.0.1.
There was one complaint received in this reporting month.
9.0.2.
A water impact complaint was received by ET on 21
August 2012 (ICC Ref. No.: 1-375813738 dated 20 August 2012, forwarded by RSS).
The complaint was reported by Mr. Ho that turbid appearance in water quality
generated from dredging operation at the exit of CBTS and lighthouse from two
barges respectively in construction sites of CBTS on 18 and 19 August 2012 between
3:00 and 10:00pm. The complainant requested a follow-up and reply from relevant
department.
9.0.3.
ET
confirmed with the Resident Site Staff that seawall blocks removal at north of
TS1 and removal of amour rocks at tip of Eastern Breakwater for HY/2009/15 were
conducted during the concerned period on 18 August 2012, and seawall blocks
removal at north of TS1 during the concerned period on 19 August 2012.
9.0.4.
After
reviewing the results of water monitoring at C7 on 17 and 20 August 2012, no
exceedance was recorded and the water quality parameters were all below action
level. Site investigation for HY/2009/15 was conducted on 21 August 2012. The
investigation found that inadequate silt curtain for protecting trimming work
at northern side of TS1, impermeable barrier were observed inadequate to
protect the removed seawall location for trimming and dredging at TS1 and inadequate
silt curtain were observed for protecting trimming work at breakwater at TS1.
Reviewing the photo records of the concerned areas provided by RSS and
investigations by RSS, it was found that the silt curtains around the concerned
areas of northern TS1 and Eastern Breakwater were inadequate, and the silt
curtains provided at both ends of the derrick barge were not fully enclosed. Also, after work, the silt curtains were
not properly maintained to surround the affected work areas, causing silt water
leakage into the
9.0.5.
HyD
made a reply to the complainant on 23 August 2012 by phone. HyD replied that
there would be on-going activities in the north side of TS1 and the end tip of
Eastern Breakwater included filling and rock removal works. HyD explained to
the complainant that the Contractor has deployed silt curtain to safeguard the
water quality in the vicinity, but the silt curtain deployment requires further
improvement. RSS has immediately urged the Contractor to implement mitigation
measures and also stepped up supervision on Contractor¡¦s work. RSS would
continue to work with the Contractor on the effectiveness of the environmental
mitigation measures implemented on site, and the Contractor would take into
account of ET and IEC¡¦s recommendations to enhance the environmental mitigation
measures. No further complaint was
received after the response.
9.0.6.
The details of cumulative complaint log and updated
summary of complaints are presented in Appendix 9.1.
9.0.7.
Cumulative statistic on complaints and successful
prosecutions are summarized in Table 9.1 and Table 9.2
respectively.
Table 9.1 Cumulative
Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement works (Mar 2010) to last
reporting month |
26 |
August 2012 |
1 |
Project-to-Date |
27 |
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1.
The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
10.0.2.
WDII/RSS
advised that the dredging works for submarine pipeline at
10.0.3.
Water
quality monitoring at WSD10 and WSD15 will be temporary suspended while water
quality monitoring at WSD9 and WSD17 were implemented with respect to
HK/2009/02 for the water quality monitoring scheduled on 8 Feb 12 onwards;
10.0.4.
Water
quality monitoring at C8 and C9 have been implemented with respect to
HY/2009/19 since the marine bore
piling work started on 28 January 2012.
10.0.5.
Based
on the safety concern when external façade refurbishment was conducted by
contractor employed by Provident Centre (C9) between 9 January 2012 to 30 July
2012 which caused to the inaccessibility of sampling either land and marine
since 3 Feb 2012, there is a fine adjustment of the sampling location of water
quality monitoring at C9 since 10 March 2012 to the closest accessible point
prior to the completion of the external façade refurbishment work.
10.0.6.
Due
to the access of water monitoring station at WSD19 was blocked by LCSD
construction works from 3 April 2012 to 2 May 2012 and lead to the
inaccessibility of sampling either land and marine, there is a fine adjustment
of the sampling point of WSD 19 since 5 April 2012 to the closest accessible
point prior to the completion of the construction activities.
10.0.7.
With respect to the trial
dredging at WCR2 was scheduled on 20, 22, 24, 25 March and 1, 3, 11, 13, 15, 17, 19, 20 Apr and 3 May 2012, on-going water quality monitoring results at WSD21 during
this period was checked and indicated that there was no contribution due to the
trial dredging operation. Enhanced review of water quality around WCR2
was also implemented and no deterioration in the water quality was observed.
10.0.8. Due to the dredging works for Cross Harbour Water Mains from Wan
Chai to Tsim Sha Tsui- DP6 was completed on 26 March 2012, the temporary
suspension of impact water quality monitoring at WSD7 and WSD20 after 27 April
2012 for the water quality monitoring at WSD7 and WSD20 have been monitored for
4-week period after the completion of DP6 to confirm no water deterioration.
10.0.9.
The scheduled construction activities and the
recommended mitigation measures for the coming month are listed in Table
10.1.
Table 10.1 Construction
Activities and Recommended Mitigation Measures in Coming Reporting Month
Contract No. |
Key Construction Works |
Recommended Mitigation Measures |
HK/2009/01 |
Marine Works (at Wan Chai) ¡P
Reclamation works within HKCEC Water Channel
(from CH170 to CH220) ¡P
Rockfilling for formation of rock bund within
HKCEC Water Channel (from CH220 to CH230) ¡P
Installation pipe pile wall for modification of
vertical seawall near ¡P
Rockfilling at northeast of Area 9 and Area7
near ¡P
Demolition of Wan Chai West Ferry Pier ¡P
Cross-Harbour Watermains Installation (CHA
& CHB) Trust block construction, concrete coating for flange joint and
rockfilling protection works for cross-harbour watermains in Victoria Harbour ¡P
Reinstatement works at TST seashore including
removal of silt screen and dismantling of jack-up barge Fresh Watermains, Cooling Watermains and Salt Watermains
(On Land) ¡P
Zone B1-5A, B2-1, B4-1A, B4-3, B5-1, B5- 3,
A1-1, A1-2, A1-3B, A2-2, A3-2A, A3-4B, A3-5B, A4-2A ¡P
Mainlaying works and G.I. ducting works at Zone
B1-5A, B4-1A and B4-3 ¡P
Mainlaying works at Zone B3-1 ¡P
Mainlaying works across the run-out of
Renaissance Harbour View Hotel by open-cut method ¡P
Mainlaying works at ¡P
Mainlaying works at traffic island near
junction between ¡P
Pipe laying works at Zone A3-2A would be
completed and heading no. H1 ¡P
Mainlaying works at Zone A3-5B of ¡P
No. H6C excavation works. ¡P
Pipe laying works for cross harbour watermains
within HKCEC water channel |
¡P
To conform the installation and setting as in
the silt screen deployment plan ¡P
Frequency spray water on the dry dusty road
and on the surface of concrete breaking ¡P
To cover the dusty material or stockpile by
impervious sheet ¡P
To space out noisy
equipment and position as far as possible from sensitive receiver. ¡P
To well maintain
the mechanical equipments / machineries to avoid abnormal noise nuisance. ¡P
Machines and plant
that may be in intermittent use should be shut down between work periods or
should be throttled down to a minimum ¡P
Daily visual inspection of silt screen and
silt curtain to ensure its operation properly |
HK/2009/02 |
¡P
Complete PTI modification works after completion
of New Public Toilet in ¡P
Complete the initial testing of P7, P8 and P9
pumping station. ¡P
Complete all cooling mains and cabling works for
P7, P8 & P9 Pumping Stations permanent power-on and signal control. ¡P
800MS pipe installation inside ¡P
ABWFs & E&M works of WSD Salt Water
Pumping Station. ¡P
Conduct Fire Service Inspection of WSD Salt Water Pumping Station ¡P
Complete the finishing works of WSD Salt Water Pumping
Station. ¡P
Complete WSD intake A and Intake B in-situ
concrete work. ¡P
Construction of Bay 1b ¡V 2, Bay 6 ¡V 8 salt water
intake culverts at WCR1 area. ¡P
Continue construction salt water intake ¡P
Commence salt water intake culvert at transition
bays inside jacking pit and receiving pit. ¡P
Continue remaining drainage works and reinstatement
works along ¡P
Commence HDPE piping on UU Bridge and inside
launching pit. ¡P
Construction for Box Culvert N1 at WCR1 area. ¡P
Complete concreting works for the Level 2 at the
New Ferry Pier. ¡P
Reclamation works at WCR2 area. ¡P
Commence drainage work to suit TWCR4
construction. ¡P
Diversion of uncharted drainage works at Box
culvert ¡§O¡¨. ¡P
Continue trial excavation and preparation works
for Hung Hing Road Diversion |
¡P
To cover the dusty material or stockpile by
impervious sheet; ¡P
Frequency spray water on the dry dusty road
and on the surface of concrete breaking ¡P
To well maintain the mechanical equipments /
machineries to avoid abnormal noise nuisance and dark smoke emission ¡P
To conform the installation and setting as in
the silt screen and silt curtain deployment
plan ¡P
Movable noise
barrier shall be deployed for demolition works ¡P
Daily visual inspection of silt screen and
silt curtain to ensure its operation properly ¡P
Review silt screen
deployment and silt curtain deployment and resubmit associate
plans to EPD ¡P
Implement silt
screen and silt curtain in accordance with the associated plans submitted to
EPD. |
HY/2009/15 |
¡P
TZ1 reclamation works ¡P
Seawall trench works at TS2 ¡P
Formation of temporary seawall at TS2 ¡P
Dredging at TS2 |
¡P
Watering
any dust generating activities ¡P
Checking
all drip trays frequently and clear any stagnant water and mud inside it. ¡P
Noise
control measures shall be provided during restricted hours. |
HK/2010/06 |
¡P
Pile head breaking ¡P
Sonic tube trimming |
¡P
To conform the installation and setting as in
the silt screen and silt curtain deployment
plan ¡P
To space out noisy
equipment and position as far as possible from sensitive receiver. ¡P
Daily visual inspection of silt screen and
silt curtain to ensure its operation properly |
HY/2009/19 |
¡P
Marine bored piling ¡P
Construction works
for Box Culvert T |
¡P
To conform the installation and setting as in
the silt screen and silt curtain deployment
plan |